CITY COMMISSION AGENDA ITEM

vertical_CityOfLawrence-7

 

Department:

Municipal Services & Operations

Commission Meeting Date: Nov. 6, 2018

Staff Contact:

Jonathan Marburger, Project Engineer

Recommendations/Options/Action Requested:

Award Bid No. B1823 for 19th Street Reconstruction – Phase B and Iowa Street & 19th Street Pedestrian Tunnels (CIP #PW18E7) to RD Johnson Excavating in an amount of $6,033,878.95. 

 

Approve Amendment No. 7, in the amount of $65,000, to Professional Engineering Consultants for additional services related to CIP #PW18E7.

 

Authorize the Mayor to execute a Supplemental City/State agreement between the City of Lawrence and the Kansas Department of Transportation for the construction of the 19th Street and Iowa Street Pedestrian/Bicycle Tunnel Project.

 

Executive Summary:

 

This project ties City improvements to 19th Street and KDOT-funded Tunnel improvements for Contractor efficiency and ease of traffic control. The scope includes:

·         19th Street Reconstruction (including pavement, sidewalk/trail, drainage, and utility improvements) from Iowa Street to Naismith Drive,

·         Northbound Right Turn Lane from Iowa Street to 19th Street

·         Traffic Signals at 19th Street/Iowa Street and 19th Street/Stewart Avenue

·         Pavement Replacement at Fire Station #5

·         Pedestrian Tunnels under Iowa Street and 19th Street

The general plan and typical section of 19th Street will include three (3) traffic lanes and bike lanes.

 

The following funding sources apply to the project:

 

Funding Source

Budgeted Amount

Fund Year

Fund Type

CIP PW18E7*

$  3,000,000.00

2018*

(revised)

Capital Improvement Reserve Fund

CIP PW18E7

$     777,681.26

2018

Intergovernmental (KDOT FFE)

CIP CI09 (Bike/Ped Funds)

$      200,000.00

2017/18

Capital Improvement Reserve Fund

CIP UT9902/UT9903

$      580,464.15

2017/18

Utility Replacement Funds

CIP PW19B7 (Fire Medical Pavement Replacement)

$      368,820.18

2019

General Obligation Debt

KDOT TA Grant

$  1,597,175.00

Intergovernmental Grant

KDOT TEA Grant

$      271,382.00

Intergovernmental Grant

University of Kansas

$      200,000.00

Intergovernmental Grant

Total Funding

 $   6,995,522.59

 

 

*Revised amount authorized July 17, 2018 with the 2018 Revised Budget

 

The following costs include all engineering services and amendments as well as the low bid:

 

Item

Amount

Vendor

Engineering (Roadway)

$ 205,000.00

PEC

Right of Way

$   33,650.00

--

Construction

 $  6,033,878.95

RD Johnson

Grand Total

 $ 6,272,528.95

 

 

The project will be completed in two construction phases:

·         Phase 1: 19th Street Construction from Iowa Street to Ousdahl Road and East Portion of Tunnel under Iowa Street.

·         Phase 2: 19th Street Construction from Ousdahl Road to Naismith Drive, 19th Street Construction from Constant Avenue to Iowa Street, and West Portion of Tunnel under Iowa Street.

 

During construction, the contractor will provide access to adjacent properties with access adjacent to 19th Street. The early start date for the project is January 7, 2019, with no impacts to the roadway allowed before March 11, 2019. The calendar substantial completion date is August 2, 2019.

 

Additional engineering services were required to avoid major fiber optic utility relocations and to develop plans for replacement of Fire Station #5 parking lot.

 

KDOT has provided an additional $271,382.00 in federal funds to the project (attached Supplemental Agreement).

 

Strategic Goal Area:

Safe, Healthy, and Welcoming Neighborhoods

Innovative Infrastructure and Asset Management

Fiscal Impact (Amount/Source):

The fiscal impact to the City for construction is $6,033,878.95. This item is included in the 2018 CIP (PW18E7) to be funded with Capital Improvement Reserve Funds, utility funds, and Intergovernmental Grants.

 

The fiscal impact to the City for additional engineering services is $65,000.

Attachments:

KDOT Supplemental Agreement

PEC Amendment 7 Fee Estimate

Bid Tabs

Previous Agenda Reports:

October 17, 2017, Regular Agenda #2

Moved from Consent Agenda Item No. 14. Authorize the acceptance of Transportation Alternative awarded funds for the 19th and Iowa pedestrian/bicycle underpass, in the amount of $1.6 million (with a $200,000 City of Lawrence local match and a $200,000 University of Kansas Local match) and the Safe Routes to School project, in the amount of $400,000 (with a $100,000 local match). Staff Memo & Attachments  Correspondence - added 10/17/17  

 

May 1, 2018, Consent Agenda #13

Authorize the Mayor to execute a City/State agreement between the City of Lawrence and the Kansas Department of Transportation for the construction of the 19th Street and Iowa Street Pedestrian/Bicycle Tunnel Project.  Staff Memo & Attachments

 

June 5, 2018

City Manager’s Report for Week Ending June 2, 2018

 

June 12, 2018, Consent Agenda #9

Adopt Resolution No. 7254, declaring the City’s intent to issue General Obligation Bonds in the amount of $500,000 for the design and construction of Sidewalk/Bike/Ped Improvements/ADA Ramps (CI09).  Staff Memo & Attachments

 

 

 

 