Project Details. In 2006 the City was informed of an $800,000 earmark for the construction of 31st Street from Haskell Avenue to O’Connell Road. The earmark does not have any conditions attached; essentially this means the funds can be used for preliminary engineering (design), right-of-way acquisition, and construction. The project will be administered by KDOT. KDOT can “charge” a 1% administration cost, leaving the total amount available at $792,000.
The City submitted a Request for Construction Project on June 15, 2006 to initiate the project. The project does have a schedule with a tentative letting of October 2008; however, we have to have the project complete in ten years so the letting date could be moved.
Project Status. The first steps to begin this project are to execute the City-State Agreement and select an engineering firm. KDOT will require “Field Check Plans” which need to be 60-70% complete prior to purchasing right-of-way.
Work items to be completed at this time include:
· Execute City-State Agreement |
· Begin consultant selection process |
· Select consultant; meet with City Manager and City Commission to discuss 31st Street Study and goals for project |
· Public process |
· “Field Check Plan” completion |
· Property acquisition |
Pending funding:
· Proceed to final plan |
· Bid/construct |
Action Request.
1. Adopt Resolution 6718 authorizing the Mayor to execute City-State Agreement 242-06.
2. Authorize distribution of Request for Qualifications for professional engineering services for the construction of 31st Street from Haskell Avenue to O’Connell Road.