| Kansas Department of Transportation | |||||||
| PROJECT SCHEDULE | |||||||
| Bureau of Local Projects | |||||||
| Geometric Improvement or Economic Development Project | |||||||
| Date Prepared: | February 8, 2007 | ||||||
| Prepared for: | City of Lawrence | ||||||
| Douglas County | |||||||
| K.D.O.T. Project Number: | 23 U-2117-01 | ||||||
| Tentative Letting Date: | October, 2008 | ||||||
| NOTICE | |||||||
| The following dates are furnished as a guide to aid in maintaining this | |||||||
| project on a schedule which will insure the letting date indicated. The | |||||||
| letting date has been tentatively set and the amount of funds and/or the | |||||||
| obligation authority available could cause the schedule to be revised. | |||||||
| If the letting date is revised or the completion of the items fluctuate | |||||||
| significantly from the established dates listed, this schedule will be re- | |||||||
| vised to indicate the new tentative letting date and project schedule. | |||||||
| Plans forwarded to BLP will not be processed without a current | |||||||
| detailed estimate. | |||||||
| Months | DEADLINE | DATE | |||||
| ITEMS TO BE COMPLETED | to | COMPLETION | COMPLETED | ||||
| Letting | DATE | -For Your Use Only- | |||||
| Field Check Plans & Estimate to BLP | 19.5 | March 5, 2007 | |||||
| Field Check Completed | 15.5 | July 4, 2007 | |||||
| Office Check Plans & Estimate to BLP | 9.5 | January 2, 2008 | |||||
| Final Check Plans & Estimate to BLP | 5.5 | May 2, 2008 | |||||
| Ks. Water Resources (DWR) Permits to BLP | 4.0 | June 16, 2008 | |||||
| R/W Clearances (1303 & 1303A Forms) to BLP | 4.0 | June 16, 2008 | |||||
| Utility Form (1304 & Agreements) to BLP | 4.0 | June 16, 2008 | |||||
| Corps of Engineers (NW or 404) Permits to BLP | 4.0 | June 16, 2008 | |||||
| Approved Final Plans & Tracings to BLP | 3.5 | July 1, 2008 | |||||