Kansas Department of Transportation
 PROJECT SCHEDULE
Bureau of Local Projects
    Geometric Improvement or Economic Development Project  
     
        Date Prepared:    February 8, 2007  
           
        Prepared for:   City of Lawrence  
      Douglas County  
           
        K.D.O.T. Project Number:   23 U-2117-01  
           
           
           
        Tentative Letting Date:   October, 2008  
     
  NOTICE  
       
       The following dates are furnished as a guide to aid in maintaining this  
    project on a schedule which will insure the letting date indicated.    The  
    letting date has been tentatively set and the amount of funds and/or the  
    obligation authority available could cause the schedule to be revised.  
           If the letting date is revised or the completion of the items fluctuate  
    significantly from the established dates listed, this schedule will be re-  
    vised to indicate the new tentative letting date and project schedule.  
       
        Plans forwarded to BLP will not be processed without a current  
                                      detailed estimate.  
       
     
      Months DEADLINE        DATE    
  ITEMS TO BE COMPLETED to COMPLETION   COMPLETED  
      Letting DATE     -For Your Use Only-  
    Field Check Plans & Estimate to BLP 19.5 March 5, 2007      
    Field Check Completed 15.5 July 4, 2007      
    Office Check Plans & Estimate to BLP 9.5 January 2, 2008      
    Final Check Plans & Estimate to BLP 5.5 May 2, 2008      
    Ks. Water Resources (DWR) Permits to BLP 4.0 June 16, 2008      
    R/W Clearances (1303 & 1303A Forms) to BLP 4.0 June 16, 2008      
    Utility Form (1304 & Agreements) to BLP 4.0 June 16, 2008      
    Corps of Engineers (NW or 404) Permits to BLP 4.0 June 16, 2008      
    Approved Final Plans & Tracings to BLP 3.5 July 1, 2008      
     
     
CC:       Rupis-2