Kansas Department of
Transportation |
PROJECT SCHEDULE |
Bureau of Local Projects |
|
|
Geometric
Improvement or Economic Development Project |
|
|
|
|
|
|
Date Prepared: |
|
February 8, 2007 |
|
|
|
|
|
|
|
|
|
Prepared
for: |
|
City of Lawrence |
|
|
|
|
Douglas
County |
|
|
|
|
|
|
|
|
|
K.D.O.T. Project
Number: |
|
23 U-2117-01 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Tentative Letting
Date: |
|
October, 2008 |
|
|
|
|
|
NOTICE |
|
|
|
|
|
|
|
The following dates are furnished as a
guide to aid in maintaining this |
|
|
project on a schedule which will insure the
letting date indicated. The |
|
|
letting date has been tentatively set and
the amount of funds and/or the |
|
|
obligation authority available could cause
the schedule to be revised. |
|
|
If the letting date is revised or
the completion of the items fluctuate |
|
|
significantly from the established dates
listed, this schedule will be re- |
|
|
vised to indicate the new tentative letting
date and project schedule. |
|
|
|
|
|
|
|
|
Plans forwarded to BLP will not be
processed without a current |
|
|
detailed
estimate. |
|
|
|
|
|
|
|
|
|
|
|
Months |
DEADLINE |
DATE |
|
|
|
ITEMS TO BE COMPLETED |
to |
COMPLETION |
COMPLETED |
|
|
|
|
Letting |
DATE |
-For Your Use Only- |
|
|
|
Field Check Plans & Estimate to BLP |
19.5 |
March 5, 2007 |
|
|
|
|
|
Field Check Completed |
15.5 |
July 4, 2007 |
|
|
|
|
|
Office Check Plans & Estimate to
BLP |
9.5 |
January 2, 2008 |
|
|
|
|
|
Final Check Plans & Estimate to
BLP |
5.5 |
May 2, 2008 |
|
|
|
|
|
Ks. Water
Resources (DWR) Permits to BLP |
4.0 |
June 16, 2008 |
|
|
|
|
|
R/W
Clearances (1303 & 1303A Forms) to BLP |
4.0 |
June 16, 2008 |
|
|
|
|
|
Utility Form (1304 &
Agreements) to BLP |
4.0 |
June 16, 2008 |
|
|
|
|
|
Corps of Engineers (NW
or 404) Permits to BLP |
4.0 |
June 16, 2008 |
|
|
|
|
|
Approved Final Plans & Tracings to
BLP |
3.5 |
July 1, 2008 |
|
|
|
|
|
|
|
|
|
CC: |
|
|
|
Rupis-2 |
|
File |
|
|
|
|
Rev-10/17/02 |
|
|
|
|
|
|
|
|