City of Lawrence

Utilities Department 

MEMORANDUM

 

TO:              David L. Corliss, City Manager

                        Cynthia Wagner, Assistant City Manager

                   Diane Stoddard, Assistant City Manager

                  

FROM:         Philip E. Ciesielski, Assistant Director of Utilities

 

CC:                        Dave Wagner, Utilities Director

                   Mike Lawless, Assistant Director of Utilities

                   Beth Frailey Krishtalka, Management Analyst

Mark Hegeman, Water and Wastewater Systems Manager

Dave King, Maintenance Manager

 

DATE:           May 19, 2010

 

RE:                  May 25, 2010 Agenda Item – Award the bid for Bid Number B1024 Project UT0705CS Wet Weather Storage Expansion for Pump Station PS09 (Four Seasons)

 

Please include the following item on the City Commission agenda for consideration at the May 25, 2010 meeting:

 

Award the bid for Bid Number B1024 Project UT0705CS Wet Weather Storage Expansion for Pump Station PS09 to the low bidder Wildcat Construction Company Inc. in the amount of $1,444,400.00 and authorize the City Manager to execute the contract.

 

Project Details

The 2003 Wastewater Master Plan identified improvements to Pump Station 09 located west of 31st and Kasold (area map) that included expansion of the wet weather storage capacity by 2.5 million gallons. The additional wet weather storage is critical to relieving collection system capacity issues and for the continuation of development in the Yankee Tank and Wakarusa Basins and along the 31st Street corridor. The project was to be one of the first projects approved for construction within the Wakarusa Water Reclamation Facility (WWRF) contract. While construction of the WWRF is on hold, there is a more immediate need for the additional storage capacity at Pump Station 09.

 

Project History

On March 11, 2008, the City Commission authorized staff to advertise a Request for Proposals for professional engineering services to expand wet weather storage at Pump Station 09.

 

On May 5, 2009 the City Commission authorized staff to negotiate an Engineering Services Agreement for design and construction phase engineering services with Black & Veatch.

 

On September 1, 2009 the City Commission authorized the City Manager to execute a design and construction phase engineering services agreement with Black & Veatch.

 

On March 22, 2010 the Planning Commission approved the Preliminary Plat and voted unanimously to forward the Rezoning Request, and Special Use Permit to the City Commission with a recommendation for approval.

 

April 6, 2010 the City Commission set a bid date of May 11, 2010.

 

April 6 & 13, 2010 the City Commission adopted the Rezoning Request Ordinance, accepted the dedication of easements and Preliminary Plat and approved the Special Use Permit for the property.

 

April 27, 2010 Department of Utilities staff and staff from Black & Veatch held a prebid meeting at the project site to review the project and bid requirements and answer questions from potential bidders, subcontractors and suppliers.

 

Project Status

On May 11, 2010 bids were received from the following seven (7) bidders.  The bids were opened and publicly read aloud.

 

B.A. Green Construction Inc.                   $1,989,000.00

BRB Contractors                          $1,729,000.00

Irvinbilt Company                         $2,356,000.00

Midland Contractors inc.                $1,777,000.00

Walters Morgan Construction Inc.   $1,717,000.00

Wildcat Construction Company Inc. $1,444,400.00

Wolfe Construction Inc.                $1,900,000.00

 

Engineer’s Opinion of Probable Cost          $2,058,000.00

 

Black & Veatch has reviewed the bids and qualifications of the low bidder and, per the attached letter and bid tabulation, recommend awarding the bid to the low bidder Wildcat Construction Company, Inc.

 

Proposed Project Schedule

Advertise for Bids               April 7, 2010

Prebid Meeting                   April 27, 2010

Bid Opening                      May 11, 2010

Award Bid                         May 25, 2010

Notice to Proceed               June 8, 2010

Project Completion             October 8, 2010

 

Project schedule is dependent on execution of contract documents, issuance of Notice to Proceed and weather conditions during construction.

 

Project Funding 

The project is funded through the reallocation of $3,500,000.00 from the 2007 revenue bond fund. The project is included in the 2009 Capital Improvement Program as well as the 2009 Rate Plan.

 

Action Request

Award the bid for Bid Number B1024 Project UT0705CS Wet Weather Storage Expansion for Pump Station PS09 to the low bidder Wildcat Construction Company Inc. in the amount of $1,444,400.00 and authorize the City Manager to execute the contract.