Memorandum

City of Lawrence

Public Works Department

 

TO:

Charles Soules

FROM:

Timothy D.  Driggs, Project Inspector

Date:

August 11, 2008

RE:

25th Terrace, O’Connell Road to Franklin Road

Street, Storm Sewer, Waterline Improvements

Project No. 12-CP2-407(BD) – City Bid No. B07065

Change Order No. 6

 

Please include the following item on the City Commission consent agenda for consideration at the August 19, 2008 meeting:

Approval of Change Order No. 6.

Total construction contract change orders to date covering all outstanding items are $94,845.47.

 

Project Details.

Major construction items included in this change order are:

 

 

Project Status.  The project is 85% complete and is scheduled to be completed within the contract allowable time.

 

Project Funding. The project is funded 100% from the benefit district.

 

ORIGINAL BID AMOUNT

$1,457,591.30

CHANGE ORDER 1

     $27,643.00

CHANGE ORDER 2

    -$21,541.00

CHANGE ORDER 3

     $37,862.00

CHANGE ORDER 4

       $6,765.00

CHANGE ORDER 5

       $4,200.00

CHANGE ORDER 6

     $38,533.54

TOTAL PROJECT COST

$1,552,436.77

 

Action Request.  Public Works staff requests approval of Change Order No. 6 in the amount of $38,533.54.

 

Respectfully Submitted,

 

Timothy D Driggs

Project Inspector

 

Attachment – Change Order No. 6