Memorandum
City of Lawrence
Public Works Department
TO: |
Charles Soules |
FROM: |
Timothy D. Driggs, Project Inspector |
Date: |
August 11, 2008 |
RE: |
25th Terrace, O’Connell Road to Franklin Road Street, Storm Sewer, Waterline Improvements Project No. 12-CP2-407(BD) – City Bid No. B07065 Change Order No. 6 |
Please include the following item on the City Commission consent agenda for consideration at the August 19, 2008 meeting:
Approval of Change Order No. 6.
Total construction contract change orders to date covering all outstanding items are $94,845.47.
Project Details.
Major construction items included in this change order are:
Project Status. The project is 85% complete and is scheduled to be completed within the contract allowable time.
Project Funding. The project is funded 100% from the benefit district.
ORIGINAL BID AMOUNT |
$1,457,591.30 |
CHANGE ORDER 1 |
$27,643.00 |
CHANGE ORDER 2 |
-$21,541.00 |
CHANGE ORDER 3 |
$37,862.00 |
CHANGE ORDER 4 |
$6,765.00 |
CHANGE ORDER 5 |
$4,200.00 |
CHANGE ORDER 6 |
$38,533.54 |
TOTAL PROJECT COST |
$1,552,436.77 |
Action Request. Public Works staff requests approval of Change Order No. 6 in the amount of $38,533.54.
Respectfully Submitted,
Timothy D Driggs
Project Inspector
Attachment – Change Order No. 6