| CITY OF LAWRENCE, KANSAS | |||||||||
| PUBLIC WORKS DEPARTMENT | |||||||||
| CONSTRUCTION CONTRACT CHANGE ORDER | |||||||||
| Project Number and Name | 12-CP2-407(BD) | ||||||||
| 25 th Terrace, O'Connell Rd To Franklin Rd | |||||||||
| Change Order No | 6 | Date | 8/11/2008 | ||||||
| Contractor Name & Address | Kings Constrruction | ||||||||
| P.O. Box 188 | |||||||||
| Oskaloosa, Ks. 66066 | |||||||||
| The following changes are being made to the referenced construction contract:that are not included in | |||||||||
| the original unit price bid items: | |||||||||
| Item No. | Description | Units | Unit Cost | Quantity (+/-) | Net Change in Contract Price ($) | ||||
| $0.00 | |||||||||
| $0.00 | |||||||||
| Changes to original unit price bid items are as follows: | |||||||||
| Item No. | Description | Units | Unit Cost | Quantity (+/-) | Net Change in Contract Price ($) | ||||
| 25 | 9" Asphalt Concrete Base Course (May) | Ton | $6.00 | 1693.84 | $10,163.04 | ||||
| 25 | 9" Asphalt Concrete Base Course (June) | Ton | $11.50 | 2467 | $28,370.50 | ||||
| 22 | 2" Asphalt Concrete Surface Course (August) | Ton | $4.50 | $0.00 | |||||
| Original Contract Amount | $1,457,591.30 | ||||||||
| Net Change by Previous Change Order(s) | $56,311.93 | ||||||||
| Net Change by This Change Order | $38,533.54 | ||||||||
| New Contract Amount | $1,552,436.77 | ||||||||
| Original Contract Time or Completion Date | 110 | ||||||||
| Net Change by Previous Change Order(s) | 0 | ||||||||
| Net Change by This Change Order | 0 | ||||||||
| New Contract Time or Completion Date | 110 | ||||||||
| Approved By: | |||||||||
| Date: | |||||||||
| Contractor | |||||||||
| Date: | |||||||||
| Project Engineer | |||||||||