Memorandum
City of
City Manager’s Office
TO: |
David L. Corliss,
City Manager |
FROM: |
|
CC: |
Mark Hecker, Parks
& Maintenance Superintendent Sandra Day, Planner |
DATE: |
May 13, 2008 |
RE: |
Status of |
On Thursday, May 1, 2008, the
Board of Zoning Appeals approved a waiver allowing for a gravel surface parking
lot for the
All of the necessary design work for the project has been completed. Before construction can begin Westar must raise their lines so that construction equipment can access the area. Now that the site plan has been approved, Westar should be able to complete that work within a few weeks. Public Works will coordinate with Parks and Recreation to complete the construction in June or July, as staff resources allow. Public Works will provide labor and Parks and Recreation will provide materials.
Attachments: