Memorandum
City of
Public Works
TO: |
David L. Corliss, |
FROM: |
Chuck Soules |
CC: |
Shoeb Uddin, |
Date: |
February 12, 2008 |
RE: |
City Project No.
15-CP5-407(BD) Maximum
Assessment Hearing February 19, 2008 Regular
Agenda Item |
Please include the following item on the City Commission regular
agenda for consideration at the February 19, 2008 meeting:
Project Description/Details. The project will include a 31 ft. street with curb and gutter, sidewalk
and multi-use path, water main, and storm sewer improvements from
Project History/Status.
4/17/07 |
City Commission approved the Mercato Addition preliminary development
plan, final plan, and accepted right-of-way easements. |
5/15/07 |
City Commission held public hearing to establish benefit district. Resolution 6661 was approved. |
8/23/07 |
City Commission approved design contract with BG Consultants. |
March 2008 |
Plans almost at final completion.
Bidding spring 2008. |
Summer 2008 |
Construction begins. |
Benefit District Information/Funding.
Estimated cost: |
$1,765,000. |
Method of Assessment: |
Front footage along the frontage of GWW
east/west and then by square
footage. |
Apportionment of Cost: |
Benefit District – 100%; City-At-Large – 0%. |
Action Request.
Conduct public hearing. Adopt Ordinance 8238 establishing the maximum
assessments for improvements to
Respectfully
submitted,
Charles F. Soules, P.E.
Director of Public
Works
CFS/je
Attachments: Ordinance
8238