Memorandum
City of
Public Works
TO: |
David L. Corliss, |
FROM: |
Chuck Soules |
Date: |
January 16, 2008 |
CC: |
|
RE: |
January 22, 2008 Agenda Item 2nd and Locust Reconstruction Work Schedule and Incentive Package |
Please include the following item on the City Commission regular agenda for consideration at the January 22, 2008 meeting:
Project Information. The
2nd and
Improvements will include increased
storm sewer capacity and a new waterline to replace a 1936 existing main. Due
to sight distance limitations southbound
KTA Projects. The KTA
proposes to begin work on the
At the December 18, 2007, City Commission meeting a discussion was held regarding coordination of the KTA and city projects. It was recommended that the city coordinate the work schedule for 2nd and Locust including completion dates, incentives and liquidated damages. Attached is the KDOT Special Provision to the Standard Specifications that will be included in the bid documents.
Per the specifications, the project is to be open to unrestricted traffic by October 18, 2008. Liquidated damages of $2,500/day will be assessed for each calendar day, excluding Sundays and holidays, until the road work is complete.
KDOT’s planting season ends in October. If the sodding and other incidental/subsidiary work is not completed on or before the October 18 completion date the contractor will have to wait until March 2009 before sod can be placed. The contract allows until March 21, 2009 to complete incidential/subsidiary items. For each day after March 21, 2009 the contractor will be charged $500/day until all incidental/subsidiary items (sodding, final cleanup, final punch list, etc.) are completed.
If the contractor completed the entire project, including all incidental/subsidiary work such as cleanup and sod, on or before September 1, 2008 the contractor would receive an incentive of $50,000. Entire project completion after September 1, but prior to October 18, 2008, the contractor would receive $1,000/day up to a maximum of $30,000. Any incentive received would be at the city’s expense since KDOT has a maximum participation.
As discussed in December, completion of this project during Phase I of the KTA construction program is recommended for the following reasons:
Incentives on Other Recent Projects.
Action Request. Approve work schedule for the 2nd and Locust reconstruction project, including incentive package.
Respectfully submitted,
Charles F. Soules, P.E.
Director of Public Works
CFS/je
Attachment: KDOT Special Provision to Standard Specifications