KANSAS DEPARTMENT OF TRANSPORTATION
SPECIAL PROVISION TO THE
STANDARD SPECIFICATIONS, 2007 EDITION
WORK SCHEDULE, SPECIFIED CALENDAR
COMPLETION DATES; LIQUIDATED DAMAGES; INCENTIVE AWARD
I. PROJECT DEFINED; NATURE OF
PROJECT
The primary operation on Project No.
40-23 U 2041-01 is the
reconstruction of intersection of
II. CALENDAR COMPLETION DATE OF OCTOBER 18, 2008
FOR COMPLETION OF ALL WORK NECESSARY TO OPEN THE PROJECT TO UNRESTRICTED
TRAFFIC; LIQUIDATED DAMAGES
A. On or before OCTOBER 18, 2008, the Contractor shall
complete all work necessary to open the project to unrestricted traffic as the
Contract Documents require.
B. Liquidated Damages. If the Contractor fails to complete
all work necessary to open the project to unrestricted traffic on or before OCTOBER 18, 2008, the Contractor shall be liable for liquidated damages. Excluding Sundays and legal Holidays, the
liquidated damages charged and owing shall be two thousand five hundred dollars ($2,500.00) per day for each
calendar day, or part thereof that the project is not open to unrestricted
traffic after OCTOBER 18, 2008.
C. The Engineer may charge damages under both
Section II.B and Section IV.B for failure to complete the work timely as
required; however, if damages are assessed on the same day, the Engineer will
not withhold more than $2,500.00 on that day.
III. EARLY COMPLETION OF WORK; INCENTIVE AWARD
If the Contractor completes all work necessary to open the project to
unrestricted traffic as the Contract Documents require including sodding, remaining,
unfinished contract pay items, subsidiary items, incidental work, final
cleanup, and final punch list, on or before SEPTEMBER 1, 2008, the Contractor is eligible for an incentive
award of fifty thousand dollars ($50,000.00).
After SEPTEMBER 1, 2008 the
incentive award shall be at the rate of one
thousand dollar ($1,000.00) for each day the work is complete including sodding, remaining, unfinished contract pay items,
subsidiary items, incidental work, final cleanup, and final punch list and
the project is open to unrestricted traffic before OCTOBER 18, 2008. The maximum incentive assessment under
this provision is limited to thirty days, for a maximum incentive of thirty thousand dollars ($30,000.00).
IV. CALENDAR COMPLETION DATE OF MARCH
21, 2009 FOR COMPLETION OF ALL WORK INCLUDING SODDING, CLEANUP; LIQUIDATED DAMAGES
A. Subsection 108.4c of the Kansas Department of
Transportation Standard Specifications for
B. Liquidated
Damages. If all sodding, remaining, unfinished contract pay items,
subsidiary items, incidental work, final cleanup, and final punch list is not
completed on or before MARCH 21, 2009,
the Contractor shall be liable for liquidated damages. Excluding Sundays
and legal Holidays, the liquidated damages charged and owing shall be five hundred dollars ($500.00) per day
for each calendar day, or part thereof that the project is not complete after MARCH 21, 2009.
C. The liquidated damages charged in Section IV.B
are in addition to the liquidated damages that may be charged under Section II.B;
however, the Engineer will not withhold more than the $2,500.00 in damages on
any one day.
01-14-08
C&M (AR/EB)