Memorandum
City of Lawrence
Utilities Department
TO: |
David Corliss, Interim City Manager Debbie Van Saun, ACM, Community Development Services |
FROM: |
Bob Brower, Field Operations Supt, Utilities |
CC: |
Dave Wagner, Assistant Director, Utilities Michael Tubbs, Management Analyst, Utilities |
Date: |
June 07, 2006 |
RE: |
June 13, 2006 City Commission Agenda |
Please include the following item on the City Commission consent agenda for consideration at the June 13, 2006 meeting.
Approve the bid # 06029 from Mayer Specialty Services, LLC for the 2006 Manhole Rehabilitation Project
History:
Part of the Utilities Department’s efforts at Inflow/Infiltration (I/I) reduction is to rehabilitate existing sanitary sewer manholes that are a source of I/I. The manholes are rehabilitated by repairing defects and then spraying on a fiber reinforced cementitious mortar. The rehabilitation process will provide a monolithic liner capable of stopping I & I and restoring structural integrity.
The Utilities Department has a multi-year plan to repair/rehabilitate manholes in older sections of the City. Manholes are selected for rehab on the basis of several factors. These factors include:
· Manhole age
· Manhole material
· Known defects based on maintenance and inspection records
· Presence of defects that may contribute inflow/infiltration
· Line segments that are in the CIPP Project Area
On June 5, 2006 bids were opened for the 2006 Manhole Rehabilitation program. The vendors also bid on costs for 2nd and 3rd year contract renewal. Six vendors bid on the project and the results are shown below.
Bidder |
2006 PVF Cost |
2006 Cost |
2007 PVF Cost |
2008 PV8 Cost |
Mayer Specialty |
$70.45 |
$158,882.36 |
$70.45 |
$70.45 |
Pyramid Excavation |
$75.17 |
$169,527.14 |
$81.00 |
$88.00 |
Ace Pipe Cleaning |
$78.50 |
$177,037.13 |
$85.50 |
$92.50 |
Utility Maint. Contractors |
$85.23 |
$192,214.96 |
$90.00 |
$98.00 |
KIM Construction |
$103.00 |
$232,290.75 |
$113.00 |
$125.00 |
Midlands Contracting |
$104.00 |
$234,546.00 |
$105.00 |
$106.00 |
Project Status:
The 2006 Manhole Rehabilitation project will include 250 manholes which translate to 2,255.25 vertical feet. The average depth of each manhole is 9 feet. Mayer Specialty Service, LLC, has proven to be a reputable contractor such as the completed for the City of Lawrence LS-41 Grout Project completed in March 2006.
Project Funding:
Funding for the 2006 CIPP Program will come from the non-bonded construction fund for 2006. 2006 CIP
Action Request:
Utility Department staff requests approval from the City Commission to authorize the Interim City Manager to execute a contract agreement and purchase order with Mayer Specialty Service, LLC in the amount of $158,882.36 to complete the 2006 Manhole Rehabilitation Project.
Thank you for your assistance. Please advise if you have any questions.