CITY COMMISSION AGENDA ITEM |
|
Department: |
Utilities |
Commission Meeting Date: December 12, 2017 |
||||||||||||||||||||||||||
Staff Contact: |
Andy Ensz, Utilities Project Engineer |
|||||||||||||||||||||||||||
Recommendations/Options/Action Requested: |
|
|||||||||||||||||||||||||||
Authorize the City Manager to execute Change Order No. 5 with Crossland Heavy Contractors for the Clinton Water Treatment Plant Phase 1 Improvements Project UT1209 increasing the construction contract by $4,698.00 and allowing 30 days for installation of the mixers after mixer delivery. |
|
|||||||||||||||||||||||||||
Executive Summary: |
Change Order No. 5 to the construction contract includes the following items of work that were required after substantial completion based on operational issues with the liquid lime system. Burns & McDonnell and Staff have reviewed the proposed Change Order No. 5 and recommend authorizing its execution.
Change Order No. 5
Contract
Change order cost adjustments are 5.6% of the original contract amount. The construction contract total including Change Order No. 5 is within the original project budget. |
|||||||||||||||||||||||||||
Strategic Plan Critical Success Factor |
Innovative Infrastructure and Asset Management |
|||||||||||||||||||||||||||
Fiscal Impact (Amount/Source): |
The funding for this project is included in the Department of Utilities Rate Plan and Utilities 2017 Amended Capital Improvement Plan for UT1209 Clinton Water Treatment Plant Improvements Phase 1. |
|||||||||||||||||||||||||||