Authorize the City Manager to sign the Airport Preservation Agreement with the Kansas Department of Transportation (KDOT) for Apron Pavement Replacement (Project Number PW1715, CIP PW17A3). |
|
|||||||||||
Executive Summary: |
The City has been awarded a grant opportunity through the Kansas Airport Improvement Program from KDOT. The project would replace deteriorating apron area on the west side of the airport near the KU hangar. The project scope is depicted in the attached map.
Estimated Total Project Cost - $165,060. The project will be funded by:
This project will be constructed in 2018. If approved, the 2018 CIP will be updated to include project PW17A3CIP.
|
|||||||||||
Strategic Plan Critical Success Factor |
Non-motorized Transportation Infrastructure |
|||||||||||
Fiscal Impact (Amount/Source): |
The City’s cost will be $15,000 funded out of the Airport Fund. |
|||||||||||