CITY COMMISSION AGENDA ITEM

vertical_CityOfLawrence-7

 

Department:

Utilities

Commission Meeting Date:  May 2, 2017

Staff Contact:

Nicholas Hoyt, I/I Manager

Recommendations/Options/Action Requested:

 

Authorize the City Manager to execute Supplemental Agreement No. 4 to the existing Engineering Services Agreement, in the amount of $570,032 with TREKK Design Group, LLC for Project UT1305 Rapid Inflow and Infiltration Reduction.

 

Executive Summary:

The 2012 Wastewater Master Plan and Capital Improvements Program recommended a Rapid Inflow and Infiltration Reduction Program within the area of the City that generally flows by gravity to the Kansas River WWTP (KRWWTP). This older area of the City has the largest influence on the peak wet weather flows at the KRWWTP due to its proximity to the plant and higher levels of inflow and infiltration. The goal of the program is to reduce wet weather inflow and infiltration into the sanitary sewer system in order to eliminate the need for large scale capacity expansion projects in the Burrough’s Creek interceptors and the KRWWTP. The program, which was initiated in 2013, is planned over an eight year period using a phased approach. The program’s accomplishments, ongoing work and future work are explained in the map attached to this memorandum.

 

Staff has negotiated an appropriate scope and fee for the next phase of the program. The total fee for this phase of services is $732,032, but the cost to the City is partially offset by savings of $162,000 realized this year through a reduction in scope of Supplemental Agreement No. 1.

 

Supplemental Agreement No. 4 addresses the scope of work for the Phase 5 and 6 areas. The Phase 5 scope of work includes the following:

 

·         Public sanitary sewer system investigations which includes 365 manhole inspections, 5 public sector dye tests, and 15,000 feet of CCTV inspections

  • Continuing the Private I/I Abatement Program which includes building inspections for 1,353 buildings and 75 private sector dye tests
  • Private I/I disconnect program for 453 buildings

 

Work items for Phase 6 include smoke testing approximately 55,000 feet of sanitary sewer in Downtown Lawrence and the surrounding neighborhood. Extensive planning, observation, and public coordination efforts are included in this contract due to the sensitivity of this area. In order to minimize any potential disruption to the general public and private businesses, staff plans on completing this work with several crews working simultaneously between 6 am and 10 am on two days over the summer. Finalizing those dates will be part of the upcoming coordination and communication effort with other City Departments and Downtown Organizations.

 

Phase 6 private plumbing evaluations and other public sector investigation work is anticipated to begin in 2018 and will be completed under a future agreement.

 

Strategic Goal Area:

Innovative Infrastructure and Asset Management

Commitment to Core Services

Collaborative Solutions

Fiscal Impact (Amount/Source):

Prior to supplemental agreement No. 4, total compensation for the contract with TREKK Design Group was $3,016,859. The total fee for Supplemental Agreement No. 4 is $732,032 but that cost is partially offset by savings of $162,000 realized this year from the reduction in scope of Supplemental Agreement No. 1. Approval of Supplemental No. 4 will bring the total compensation to $3,586,891 for the contract since 2013.

 

Funding for this project is included in the Department of Utilities 2017 Amended Capital Improvement Program for Project UT1305 Rapid Inflow and Infiltration Reduction Program (CIP# 1795).

Attachments:

Rapid Inflow and Infiltration Reduction Program Phase Map

 

 

 

Reviewed By:

(for CMO use only)

TM

DS

CT

BM