CITY COMMISSION AGENDA ITEM |
|
Department: |
Utilities |
Commission Meeting Date: 2/7/2017 |
||||||||||||||||||||||||||||||
Staff Contact: |
Nicholas Hoyt, I/I Manager |
|||||||||||||||||||||||||||||||
Recommendations/Options/Action Requested: |
|
|||||||||||||||||||||||||||||||
Authorize the City Manager to execute Change Order No. 2 with SAK Construction, LLC for Project UT1508 – 2015 Sanitary Sewer Rehabilitation increasing the construction contract by $71,436.50 and 102 days. |
|
|||||||||||||||||||||||||||||||
Executive Summary: |
Part of the Utilities Department’s efforts at sanitary sewer inflow and infiltration reduction (I/I) includes repairing and reconstructing existing sewer lines that are a source of I/I. Cured in Place Pipe (CIPP) is one of the methods used. The CIPP method involves lining the inside of older deteriorated pipes without excavation. Therefore, there is very little disruption above ground. Change Order No. 2 to the construction contract includes the following items of work that were additional items requested by the City.
Change Order No. 2
Contract and Change Order History Contract
Change order cost adjustments are 15.40% of the original contract amount.
Schedule
Staff has reviewed the proposed Change Order No. 2 and recommends authorizing its execution.
|
|||||||||||||||||||||||||||||||
Strategic Goal Area: |
Infrastructure |
|||||||||||||||||||||||||||||||
Fiscal Impact (Amount/Source): |
The project is included in the Department of Utilities Rate Plan and Bonded Capital Improvement Program per Resolution 7062. The improvements were originally identified and budgeted for the upcoming 2017 CIPP Project but this work will be completed as a change order to the 2016 contract to meet the schedule requirements for the 23rd Street project upcoming this summer (2017). |
|||||||||||||||||||||||||||||||