Memorandum

City of Lawrence

Utilities Department

 

TO:

Thomas M. Markus – City Manager

Diane Stoddard – Assistant City Manager

Casey Toomay – Assistant City Manager

FROM:

Steven Craig – Utilities Manager

CC:

Dave Wagner – Utilities Director

Mike Lawless – Utilities Deputy Director

Melinda Harger – Utilities Engineer

Mark Hegeman – Utilities Superintendent

Beth Krishtalka – Assistant to Director

Carolyn Woodhead – Utilities Manager

DATE:

July 20, 2016

RE:

Process Instrumentation for Wakarusa River Wastewater Treatment Plant; UT1304

 

Background

Process instrumentation equipment and controllers are critical components in monitoring wastewater treatment processes. Currently under construction with an expected early 2018 online date, the Wakarusa River Wastewater Treatment Plant needs these items installed and functional prior to commencement of treatment operations.

 

Staff has negotiated sole source quotes from Hach Company for a combined total purchase price of $55,007.22, including related service plan. Hach is a sole source provider to ensure necessary compatibility and uniformity of this operational equipment.

 

Funding

Purchase will be funded from Utilities bond funds.

 

Action

Authorize the sole source purchase of process instrumentation equipment and controllers from Hach Company for the combined total purchase price of $55,007.22 for Wakarusa River Wastewater Treatment Plant (UT1304).