Memorandum
City of Lawrence
Utilities Department
TO: |
Thomas M. Markus City Manager Diane Stoddard Assistant City Manager Casey Toomay Assistant City Manager Brandon McGuire Assistant to the City Manager |
FROM: |
Troy Shaw Project Engineer |
CC: |
Dave Wagner Director of Utilities Mike Lawless Deputy Director of Utilities Philip Ciesielski Asst. Director of Utilities Beth Krishtalka Assistant to Director Bob Brower Utilities Operations Superintendent Scott Fewins Utilities Manager |
DATE: |
July 1, 2016 |
RE: |
Authorize the City Manager to execute change order No. 4 for the Michigan/Arkansas, 2nd Street to 4th Street Waterline Replacement Project, UT1427. |
Background
The Michigan/Arkansas Street 2nd Street to 9th Street waterline replacement project was evaluated as part of a preliminary design report, which established viable alternatives for alignment, project prioritization, construction cost estimates, and sequencing that will align with planned street rehabilitation work and budgeted funding. The assessment study identified the Michigan/Arkansas Street from 2nd Street to 9th Street waterline as a priority for replacement due to the size, age, and condition of the 6 and 8, 1922, 1958, and 1959 cast iron main. In addition to the Michigan/Arkansas section, this project will also replace the existing 6, 1959 cast iron main on Florida Street from 3rd to 4th Street. Similar to the existing line on Michigan/Arkansas, the section of waterline on Florida Street from 3rd Street to 4th Street needs to be replaced due to size, age, and condition. The proximity and similar scope of work to the Michigan/Arkansas Street project affords the opportunity to complete the smaller Florida Street project in conjunction with the larger Michigan/Arkansas project.
Project Description
The Michigan/Arkansas Street, 2nd to 9th and Florida Street, 3rd to 4th Waterline Replacement Project, as shown on the attached map, includes the replacement of approximately 5,800 linear feet of 6 and 8, 1922, 1958, and 1959 cast iron main with 8 PVC waterlines. The project also includes valves, fittings, fire hydrants and other miscellaneous appurtenances for the waterline located along Michigan/Arkansas Street from 2nd Street to 9th Street and Florida Street from 3rd Street to 4th Street.
Project Details
The Utilities Departments contractor, Banks Construction, has successfully completed the Michigan/Arkansas Waterline Replacement 2nd to 9th Street and Florida Street from 3rd Street to 4th Street project, UT1427. Change Order No. 4 represents a net increase to the construction contract of $22,130.00 to adjust the final quantities to what was installed in the field. In order to keep customers in service, avoid existing utilities, and to deal with unknown field conditions; it was necessary to install additional valves, fittings and other miscellaneous appurtenances. This change order also includes additional quantities for pavement/sidewalk restoration that was needed in order to locate unknown utilities and to remove and replace street pavement and sidewalks at appropriate locations (existing joints, outside of existing cracks, etc.).
Utilities Staff have reviewed the proposed Change Order No. 4 and recommend authorizing its execution.
Construction Contract Costs |
|
Original Contract |
$1,141,100.00 |
Change Order No. 1 |
$28,600.00 |
Change Order No. 2 |
$5,500.00 |
Change Order No. 3 |
$9,850.00 |
Change Order No. 4 (final) |
$22,130.00 |
Current Contract Total |
$1,207,180.00 |
Change order costs represent 5.8% of the original contract.
Project Funding
The project will be funded from the Department of Utilities bonded construction fund per Resolutions 7019 and 7062.
Action
Authorize the City Manager to execute Change Order No. 4 to the existing construction contract with Banks Construction, LLC in the amount of $22,130.00 for the Michigan/Arkansas 2nd Street to 9th Street Waterline Replacement Project, UT1427.