Memorandum
City of Lawrence
Public Works
TO: |
Thomas Markus, City Manager |
FROM: |
Charles F. Soules, Director of Public Works |
CC: |
Diane Stoddard, Casey Toomay, David Cronin |
DATE: |
April 18, 2016 |
RE: |
Award bid for Project No. PW1611 – 19th Street & Ousdahl Road Intersection Improvements |
On October 27, 2015 the City Commission received an update on the University of Kansas Central District Plan.
The University of Kansas (KU) Central District Plan proposes significant improvements to current student housing. The improvements are expected to begin as early as 2016 and completion in 2017/2018 with all phases. The proposed project(s) will have access to 19th Street. Due to the scope of this project and the City’s need/plans to make improvements to 19th Street it is recommended that plans for 19th Street are coordinated with KU’s plans.
The existing 19th Street from Iowa Street to Naismith Drive has a Pavement Condition Index (PCI) of 44 (which is low for this type of facility-arterial) including rutting, raveling and base failures. The curb and gutter is also in a fair condition with some areas rated as poor. This section of 19th Street is included with the projects funded with the Infrastructure Sales Tax in 2019. The proposed improvements would include a center turn lane, bike lanes, and sidewalks on both sides.
With the Central District Plan proceeding, both City and KU staff agree that planning for the coordination of these projects is essential. City water mains as well as other private utilities will have to be relocated and it is important that we have sufficient plans for 19th Street to ensure that they will not have to relocate twice. Also grades for the street as well as improvements (driveways) need to be coordinated so we are not replacing new improvements. Finally, we need to make sure that we have sufficient right-of-way to make the street improvements.
The intersection at 19th & Ousdahl Road is a key component to the Central District improvements, 19th Street, and neighborhood access. KU has funding to complete Ousdahl north of 19th, and the signalization of the intersection. Timing for completion of this intersection this summer would also be beneficial during the reconstruction of 19th Street, from Naismith to Iowa Street. If the intersection is completed it would provide an option for the phasing of construction of 19th, allowing more efficient construction.
On March 2, 2016, a public meeting was held to discuss the proposed improvements to 19th Street and construction of the intersection at Ousdahl Road. Approximately 40 residents attended.
The plan for the construction of the intersection includes:
· Construction of Ousdahl Road north of 19th Street, begin in April/ May
· Close the intersection at 19th & Ousdahl in after commencement and re-open 19th before classes resume in August
· In August/September the southern portion of Ousdahl would be completed
Bids were received on May 10, 2016:
VENDOR |
TOTAL BID |
Engineer’s Estimate |
$869,202.50 |
R.D. Johnson Excavating Co., Inc. |
$685,629.40 |
Crossland Heavy Contractors, Inc. |
$778,700.00 |
Kansas Heavy Construction LLC |
$907,965.95 |
Freeman Concrete Construction, LLC |
$1,003,513.90 |
Kissick Construction Company |
$1,038,055.35 |
Action
Award bid to R.D. Johnson Excavating Co., Inc. for Project PW1611, 19th Street & Ousdahl Road, Intersection Improvements in the amount of $685,629.40, provided the contractor can meet the terms established in the contract documents.