| CITY OF LAWRENCE, KANSAS | |||||||||
| PUBLIC WORKS DEPARTMENT | |||||||||
| CONSTRUCTION CONTRACT CHANGE ORDER | |||||||||
| Project Number and Name | PW-1330 | ||||||||
| Regional Detention | |||||||||
| Change Order No | 2 | Date | 3/16/2016 | ||||||
| Contractor Name & Address | R.D. Johnson Excavating Company | ||||||||
| 1705 N. 1399 Road | |||||||||
| Lawrence, KS 66046 | |||||||||
| The following additions and/or deletions are being made to the referenced construction contract: | |||||||||
| Item No. | Description | Units | Unit Cost | Quantity (+/-) | Net Change in Contract Price ($) | ||||
| 4 | Common Excavation | CUYD | $3.00 | 14777.75 | $44,333.25 | ||||
| 5 | Embankment | CUYD | $0.80 | 14777.75 | $11,822.20 | ||||
| 21 | Common Excavation (contractor furnished - offsite) | CUYD | $7.30 | -6230.4 | -$45,481.92 | ||||
| 22 | KDHE required unclassified excavation in drainage channel | LS | $6,780.00 | 1 | $6,780.00 | ||||
| 23 | Expose and reroute 2" line traversing the outfall drainage channel | LS | $2,350.00 | 1 | $2,350.00 | ||||
| Changes to original unit price bid items are as follows: | |||||||||
| Item No. | Description | Units | Unit Cost | Quantity (+/-) | Net Change in Contract Price ($) | ||||
| 21 | Common Excavation (contractor furnished - offsite) | CUYD | $5.00 | 6230.4 | $31,152.00 | ||||
| Original Contract Amount | $649,919.50 | ||||||||
| Net Change by Previous Change Order(s) | $210,343.00 | ||||||||
| Net Change by This Change Order | $50,955.53 | ||||||||
| New Contract Amount | $911,218.03 | ||||||||
| Original Contract Time or Completion Date | 11/21/2014 | ||||||||
| Net Change by Previous Change Order(s) | |||||||||
| Net Change by This Change Order | |||||||||
| New Contract Time or Completion Date | 5/30/2016 | ||||||||
| Approved By: | |||||||||
| Date: | |||||||||
| Contractor | |||||||||
| Date: | |||||||||
| Project Engineer | |||||||||