Memorandum

City of Lawrence

Parks & Recreation Department

 

TO:

Diane Stoddard, Interim City Manager

CC:

Casey Toomay, Assistant City Manager

Ernie Shaw, Interim Director, Parks & Recreation

FROM:

Mark Hecker, Assistant Director, Parks and Recreation

DATE:

February 19, 2016

RE:

Set Bid Date – Holcom Park Center HVAC Repairs.

 

The City of Lawrence Parks and Recreation Department requests Commission approval to set a bid date of March 22, 2016 for the repair of the Holcom Park Center HVAC system. 

 

Project Description

In the fall 2015, one of the main compressor units on the Holcom Park Center air-conditioning system failed. This portion of the system cools the lobby, meeting rooms, offices, restrooms and weight room. Some of the equipment associated with this compressor is original equipment dating back to the 1980’s when the building was constructed. The proposed project will replace the exterior compressor unit and the coils inside the air handler. This work must be completed this spring to allow the buildings air conditioning to function.

 

Project Funding

The engineers estimate for this project is $70,000. The project will be funded using funds budgeted in the 2016 Sales Tax Reserve Fund for the repairs and maintenance of Parks & Recreation facilities.

 

Action Requested

The City of Lawrence Parks and Recreation Department requests Commission approval to set a bid date of March 22, 2016 for the repair of the Holcom Park Center HVAC system.