Memorandum
City of Lawrence
Utilities Department
TO: |
Diane Stoddard – Interim City Manager Casey Toomay - Assistant City Manager Brandon McGuire – Assistant to the City Manager |
FROM: |
Nicholas Hoyt – I/I Manager |
CC: |
Dave Wagner – Director of Utilities Mike Lawless – Deputy Director of Utilities Philip Ciesielski – Assistant Director of Utilities Beth Krishtalka – Assistant to Director Bob Brower – Utilities Operations Superintendent |
Date: |
December 22, 2015 |
RE: |
Execute Supplemental Agreement No. 2 to the Existing Engineering Services Agreement for Project UT1402 City of Lawrence Flow Monitoring Program for 2016 sanitary sewer flow monitoring services. |
Background
The City of Lawrence is implementing a Rapid Inflow and Infiltration (I/I) Reduction Program. The objective of the Rapid I/I Program is an overall 35% reduction of I/I within the project area. This will amount to removal of approximately 19 MGD of peak I/I occurring during the 10-year design storm. Reducing I/I by 35% eliminates the need to construct projects that address system capacity deficiencies in the Burroughs Creek interceptors and the need for wet weather treatment capacity expansion at the Kaw WWTP.
The flow data collected as part of this project will be used to determine the effectiveness of the Rapid I/I Reduction Program, perform sewer system capacity assessment, characterize flows within basins, address wet weather problems, calibrate/verify the sanitary sewer model, and guide I/I removal efforts moving forward.
Project History
On March 25, 2014, the City Commission authorized the City Manager to Execute an Engineering Services Agreement, in the amount of $179,595 with George Butler Associates, Inc. for 2014 services associated with UT1402 – City of Lawrence Flow Monitoring Program. On December 16, 2014, the City Commission authorized the City Manager to Execute Supplemental Agreement No. 1, in the amount of $198,644 with George Butler Associates, Inc. for 2015 services associated with UT1402 – City of Lawrence Flow Monitoring Program.
Project Status
Staff has negotiated an appropriate scope and fee for 2016 flow monitoring services at 29-flow monitoring and 5 rainfall-monitoring locations. The scope for the 2016 project includes:
Flow monitoring services will be required throughout the 8 year Rapid I/I Reduction Program. If the service provided by the consultant is satisfactory to the City and the consultant is willing, staff anticipates that a flow monitoring contract will be negotiated each year with George Butler Associates, Inc. The contract scope will vary yearly adjusting to the needs of the program.
A summary of the project ESA is provided below:
Original ESA for 2014 Services: |
$179,595 |
Supplemental Agreement No. 1 for 2015 Services |
$198,644 |
Supplemental Agreement No. 2 for 2016 Services |
$205,284 |
New Contract Amount: |
$583,523 |
Project Funding
The project is included in the Department of Utilities 2016 Operations and Maintenance Budget and 2016 Capital Improvement Budget.
Action
Authorize the Interim City Manager to execute Supplemental Agreement No. 2 in the amount of $205,284 with George Butler Associates, Inc. for Project UT1402 City of Lawrence Flow Monitoring Program for 2016 sanitary sewer flow monitoring services.