Set Bid Date for Bid No. B1555 – PVC Pipe for Watermain Installations, Rehabilitation and Replacement |
Project Description
The Utilities Department requests approval to set a bid date for 2,200 feet of PVC pipe needed for watermain installations, rehabilitation, and replacement to ensure continued system capacity, integrity, and reliability.
Project Funding
Purchase will be funded from the Utilities Operations and Maintenance Budget.
Action
Set a bid opening date of November 24, 2015, for Bid No. B1555 – PVC Pipe for watermain installations, rehabilitation, and replacement.