Memorandum
City of Lawrence
Parks & Recreation Department
TO: |
David Corliss, City Manager |
CC: |
Toni Wheeler, City Attorney Ernie Shaw, Interim Director, Parks & Recreation |
FROM: |
Mark Hecker, Assistant Director, Parks and Recreation |
DATE: |
November 13, 2014 |
RE: |
Sports Pavilion Lawrence – Construction Change Orders |
Below are the change orders that were processed for the Sports Pavilion Lawrence facility as it was being constructed. All of these items are things that we requested outside of the contract agreement. All have been paid using a separate purchase order.
Project Description
Change Order #1 - Concure for track concrete, mop sink, electric outlets |
$31,962 |
CC Approved 5/20/14 Sales Tax Reserve |
Change order #2 for multi-purpose room wall, concessions wall header, floor blocking on gym floor #1 and #2 |
$26,847 |
CC Approved 7/1/14 Sales Tax Reserve |
Dehumidification of building - split cost with contractor |
$12,350 |
CC Approved 7/1/14 Sales Tax Reserve |
Change Order #3 for electrical upgrades for TV's and added outlets |
$14,492 |
CC Approved 7/8/14 Sales Tax Reserve |
Change Order #4 in-fill wall connector plates on concrete walls and painting sprinkler pipes on lower level |
$8,828 |
Sales Tax Reserve |
Change order to add electric, water and pickleball to tennis courts |
$6,150 |
CC Approved 6/24/14 Sales Tax Reserve |
Sales Tax Reserve for Change Orders at SPL - Sub Total |
$100,629 |
|