Lawrence West Apron Reconstruction |
|
|
|
|
|
Estimate |
|
ITEM |
DESCRIPTION |
UNIT |
QUANTITY |
UNIT PRICE IN FIGURES |
AMOUNT IN FIGURES |
|
1 |
Mobilization |
L.S. |
1 |
$20,000.00 |
$20,000.00 |
|
2 |
Contractor Construction Staking |
L.S. |
1 |
$10,000.00 |
$12,000.00 |
|
3 |
Demolition |
L.S. |
1 |
$20,000.00 |
$20,000.00 |
|
4 |
Unclassified Excavation |
Cu. Yd. |
1,000 |
$15.00 |
$15,000.00 |
|
5 |
Embankment In Place |
Cu. Yd. |
1,000 |
$10.00 |
$10,000.00 |
|
6 |
Crushed Aggregate Base Course (6") |
Sq. Yd. |
5,200 |
$10.00 |
$52,000.00 |
|
7 |
Bituminous Pavement |
Ton |
1,500 |
$100.00 |
$150,000.00 |
|
8 |
Pavement Marking |
L.S. |
1 |
$5,000.00 |
$5,000.00 |
|
8 |
Trench drain materials |
L.S. |
1 |
$32,000.00 |
$32,000.00 |
|
9 |
Safety Barricades |
L.S. |
1 |
$2,000.00 |
$2,000.00 |
|
10 |
Seeding |
M.S.F. |
5.0 |
$100.00 |
$500.00 |
|
11 |
Mulching |
M.S.F. |
5.0 |
$100.00 |
$500.00 |
|
PAVING TOTAL |
|
$319,000.00 |
|
15 PERCENT CONTINGENCY |
|
$47,850.00 |
|
|
|
|
TOTAL PROJECT COST |
|
$366,850.00 |
|
|
|
|
|
|
|
|
12 |
Survey |
|
|
|
$ 6,000.00 |
|
13 |
Geotech Report |
|
|
|
$ 6,000.00 |
|
14 |
Engineering |
|
|
|
$ 35,000.00 |
|
15 |
Inspection |
|
|
|
$ 20,000.00 |
|
|
|
DESIGN TOTAL |
$ 67,000.00 |
|
|
|
|
PROJECT GRAND TOTAL |
$433,850.00 |
|
|
|
|
|
|
|
|
|