Lawrence Taxiway C Reconstruction |
|
|
|
|
|
|
Estimate |
|
|
ITEM |
DESCRIPTION |
UNIT |
QUANTITY |
UNIT PRICE IN FIGURES |
AMOUNT IN FIGURES |
|
|
1 |
Mobilization |
L.S. |
1 |
$20,000.00 |
$20,000.00 |
|
|
2 |
Contractor Construction Staking |
L.S. |
1 |
$10,000.00 |
$10,000.00 |
|
|
3 |
Demolition |
L.S. |
1 |
$15,000.00 |
$15,000.00 |
|
|
4 |
Unclassified Excavation |
Cu. Yd. |
500 |
$15.00 |
$7,500.00 |
|
|
5 |
Embankment In Place |
Cu. Yd. |
500 |
$10.00 |
$5,000.00 |
|
|
6 |
Crushed Aggregate Base Course (6") |
Sq. Yd. |
1,800 |
$12.00 |
$21,600.00 |
|
|
7 |
Bituminous Pavement |
Ton |
600 |
$100.00 |
$60,000.00 |
|
|
8 |
Pavement Marking |
L.S. |
1 |
$10,000.00 |
$10,000.00 |
|
|
9 |
Seeding |
M.S.F. |
20.0 |
$100.00 |
$2,000.00 |
|
|
10 |
Mulching |
M.S.F. |
20.0 |
$100.00 |
$2,000.00 |
|
|
PAVING TOTAL |
|
$153,100.00 |
|
|
|
|
15 PERCENT CONTINGENCY |
|
$22,965.00 |
|
|
|
|
|
TOTAL PROJECT COST |
|
$176,065.00 |
|
|
|
|
|
|
|
|
|
|
11 |
Survey |
|
|
|
$ 4,000.00 |
|
|
12 |
Geotech Report |
|
|
|
$ 6,000.00 |
|
|
13 |
Engineering |
|
|
|
$ 15,000.00 |
|
|
14 |
Inspection |
|
|
|
$ 10,000.00 |
|
|
|
|
DESIGN TOTAL |
$ 35,000.00 |
|
|
|
|
|
|
|
|
PROJECT GRAND TOTAL |
$211,065.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|