Lawrence Taxiway C Reconstruction
 Estimate
 ITEM DESCRIPTION UNIT  QUANTITY  UNIT PRICE IN FIGURES AMOUNT IN FIGURES
1 Mobilization L.S. 1 $20,000.00 $20,000.00
2 Contractor Construction Staking L.S. 1 $10,000.00 $10,000.00
3 Demolition L.S. 1 $15,000.00 $15,000.00
4 Unclassified Excavation Cu. Yd. 500 $15.00 $7,500.00
5 Embankment In Place Cu. Yd. 500 $10.00 $5,000.00
6 Crushed Aggregate Base Course (6") Sq. Yd. 1,800 $12.00 $21,600.00
7 Bituminous Pavement Ton 600 $100.00 $60,000.00
8 Pavement Marking L.S. 1 $10,000.00 $10,000.00
9 Seeding M.S.F. 20.0 $100.00 $2,000.00
10 Mulching M.S.F. 20.0 $100.00 $2,000.00
PAVING TOTAL $153,100.00
15 PERCENT CONTINGENCY $22,965.00
TOTAL PROJECT COST $176,065.00
11 Survey  $       4,000.00
12 Geotech Report  $       6,000.00
13 Engineering  $     15,000.00
14 Inspection  $     10,000.00
DESIGN TOTAL  $     35,000.00
      PROJECT GRAND TOTAL $211,065.00