Memorandum

City of Lawrence

Public Works

 

TO:

Chuck Soules, Public Works Director

FROM:

David P. Cronin, City Engineer

CC:

Mark Thiel, Assistant Public Works Director

Date:

July 15, 2013

RE:

23rd Street Access Management Improvements

 

Project PW1324 - Improvements at Myers Liquor and Jiffy Lube

Authorize City Manager to execute development agreement

 

Project PW1325 - Improvements at Chipotle and Car Toyz

Authorize City Manager to execute development agreement

 

Authorize Mayor to sign city/state Supplemental Agreement No. 3 for Orscheln project

 

Project History

In April 2004, the city was awarded an Economic Development Grant from KDOT for consolidation of access points along 23rd Street from Iowa to Louisiana. Consolidation of access points improves traffic flow and safety. According to the city-state agreement, KDOT would pay 75% of actual construction costs up to a maximum of $500,000 while City costs would include engineering, right-of-way, utilities and 25% of construction costs.

 

The original project plan was to consolidate access points at some thirty different locations. Due to lack of participation by business/property owners, the original project never moved to the construction phase. Staff has been working to consolidate and reconfigure access driveways whenever opportunities arise, typically during redevelopment. Following are the six projects completed so far:

  1. Long John Silver’s restaurant
  1. CVS Pharmacy/El Mezcal
  1. University Bookstore/O’Reilly Auto Parts (now Jock's Nitch & GameDay)
  1. Bryant Collision Repair
  1. Orscheln
  2. Whole Foods & Party America

 

City staff is working on three additional projects:

  1. Myers Liquor and Jiffy Lube
  1. Chipotle and Car Toyz
  1. Improvements at northeast corner of 23rd & Iowa.

 

With the addition of new projects the original city/state agreement needs to be revised with a supplemental agreement.  Supplemental Agreement No. 3 for the Orscheln turn lane project ($25,000) will need to be executed prior to a supplemental agreement that will include Whole Foods, Myers Liquor and Chipotle projects.  Of the original $500,000 grant approximately $330,000 in state funds remain for future projects; approximately $50,000 will be used for 23rd & Iowa improvements at northeast corner with the 2014 intersection project.

 

Project Details - Myers Liquor and Jiffy Lube

The proposed development plan at Myers Liquor at the northwest corner of 23rd & Alabama includes the reconfiguration of the access to 23rd Street.  Both the existing Myers Liquor driveway and east Jiffy Lube driveway on 23rd Street are being removed and reconstructed into one combined driveway (see attached site plan).  The two property owners have executed a cross access easement agreement and a development agreement.

 

Project Details - Chipotle and Car Toyz

The proposed redevelopment plan at 1420 W. 23rd Street includes removal of the existing building and construction of a new Chipotle store.  The existing driveway at 1420 W. 23rd Street and the driveway for Car Toyz will be removed and a new combined driveway will be constructed (see attached site plan).  Both property owners have agreed to project and will execute development agreement.

 

Project Costs / Funding

KDOT has agreed to fund each project up to $30,000 (KDOT participation 75% and City participation of 25%).  The property owner will be responsible for costs exceeding $30,000 on each project.  A summary of the costs are as follows:

 

Project

Cost Estimate

Funding (max.)

KDOT (75%)

City (25%)

Myers Liquor

$30,195

$30,000

$22,500

$7500

Chipotle

$35,850

$30,000

$22,500

$7500

 

All project costs will be paid upfront by the property owner.  After completion of the project, City will reimburse the property owner for actual costs and expenses up to a maximum amount of $30,000.  Under the City/State agreement for the 23rd Street Access Management project, KDOT will then reimburse the City 75% of the total amount or $22,500 per project.  The city share, a total of $15,000, will be funded with street maintenance funds.

 

Project Schedule

Site construction activities have begun at Myers Liquor.  Reconstruction of the driveways will begin shortly and expected to be completed by end of summer.  Construction on the Chipotle site is expected to begin in late July.

 

Action Request

  1. Authorize City Manager to execute development agreement for project PW1324 - Access Management improvements at Myers Liquor and Jiffy Lube.
  1. Authorize City Manager to execute development agreement for project PW1325 - Access Management improvements at Chipotle and Car Toyz.
  1. Authorize mayor to sign city/state Supplemental Agreement No. 3