Project Description
The intersection of 6th & George Williams Way has been identified for signal improvements prior to an increase in development in the area. Under existing conditions a traffic signal is already warranted at this location. Approximately 3/4 mile north of the intersection is the proposed "Rock Chalk Park" development including a 180,000 square foot city recreation center and University of Kansas athletic complex including a track and field complex, soccer field and softball field. The completion of the "Rock Chalk Park" is anticipated to increase commercial and residential development in the area north and south of 6th Street around George Williams Way.
The scope of the project is only for signal improvements at the intersection at this time. The design will include pavement marking to open the second dedicated left-turn lanes for the east, west and north approaches that have already been constructed but are not currently utilized. Crosswalks and sidewalk ramp construction will be provided for the east and west legs of the intersection.
Project Status
In February 2013 the City Commission approved the engineering services contract to complete plans for signalization of the 6th & George Williams Way intersection. Plans are now complete and the necessary KDOT permits have been acquired. Public Works staff has been working with KDOT to fund improvements of intersections on W. 6th St in coordination with the 6th and K-10 interchange improvements. This is one of the projects that KDOT will reimburse the city through the highway 40 turn back agreement that the commission discussed June 18, 2013. The reimbursement is up to $250,000 for the improvements at 6th & George Williams Way; costs of the project will be paid up front by the city with $250,000 in general obligation bonds from Resolution 7027. Any costs exceeding $250,000 will be paid from the city's Capital Improvement Reserve Fund.
Project Funding
Engineering Design Services: $6,500
Construction Cost Estimate: $283,011
Total Cost: $289,511
Project Schedule
Advertise and bids: July 2, 2013
Bid date: July 16, 2013
Anticipated Start Date: August 2013
Project Completion Date: November 30, 2013
Action Requested
Set bid date of July 16, 2013 for Project PW1309 - 6th & George Williams Way Signal Improvements.
Adopt Resolution 7027 authorizing issuance of $250,000 in general obligation bonds for improvements on 6th Street and George Williams Way.