Memorandum

City of Lawrence

Public Works

 

TO:

David P. Cronin, P.E., City Engineer

 

FROM:

Matt Bond, P.E., Stormwater Engineer/Farmland Project Manager

 

CC:

Charles Soules, P.E., Director of Public Works

Mark Thiel, Assistant Public Works Director

 

Date:

June 20, 2013

 

RE:

Project PW1334 - Safety/Security Fence around the above ground storage tanks at the former Farmland Industries Nitrogen Plant Site

 

 

Project Description

With the acquisition of the former Farmland Industries Nitrogen Plant site came the maintenance cost associated with the two existing above ground storage tanks on the site.  The redevelopment work at the site has removed the existing perimeter fence along 23rd Street due to necessary site grading.  As a result the site is easily accessible raising safety and security concerns associated with the tall storage tanks.  Staff believes that it is prudent to construct a safety/security fence around each of the above ground storage tanks.  This will help to prevent individuals from climbing on the tanks as well as prevent the theft of copper wire from the electrical systems used for pumping the tanks.

 

Project Funding

The estimated project cost is $30,000.  The project is being funded with the environmental remediation fund obtained with the acquisition of the site and has been approved by the Kansas Department of Health & Environment.

 

Project Schedule

Advertise for bids: June 26, 2013

Anticipated Start Date: Early August 2013

Bid date: July 16, 2013

Project Completion Date: Early September, 2013

 

Action Request

Set bid date of July 16, 2013 for PW 1334 - Construction of Safety/Security around the two above ground storage tanks on the former Farmland Industries Plant site.