Memorandum
City of Lawrence
Public Works
|
TO: |
Charles Soules, P.E., Director of Public Works
|
|
FROM: |
David P. Cronin, P.E., City Engineer
|
|
CC: |
Mark Thiel, Assistant Director of Public Works
|
|
Date: |
February 4, 2012
|
|
RE: |
Project PW1309 - 6th & George Williams Way Design Contract for Signal Improvements |
Please include the following item on the City Commission Agenda for consideration at the February 12, 2013 meeting.
Project Description
The intersection of 6th & George Williams Way has been identified for signal improvements prior to an increase in development in the area. Under existing conditions a traffic signal is already warranted at this location. Approximately 3/4 mile north of the intersection is the proposed "Rock Chalk Park" development including an 180,000 square foot city recreation center and University of Kansas athletic complex including a track and field complex, soccer field and softball field. The completion of the "Rock Chalk Park" is anticipated to increase commercial and residential development in the area north and south of 6th Street around George Williams Way.
The scope of the project is only for signal improvements at the intersection at this time. The design will include pavement marking to open the second dedicated left-turn lanes for the east, west and north approaches that have already been constructed but are not currently utilized. Crosswalks and sidewalk ramp construction will be provided for the east and west legs of the intersection.
Project Status
Public Works sent a request to design consultants to submit a proposal for engineering services including an estimated design cost. BG Consultants submitted the lowest design cost ($6500) and has the expertise to complete the plans. BG has indicated they can have plans complete and permits submitted to KDOT prior to April 1, 2013.
Project Funding
Engineering Design Services: $6,500
Construction Cost: $175,000
Total Cost: $181,500
Design fees will be paid from the Capital Improvement Reserve Fund.
City staff is working with KDOT on potentially funding the Construction Improvements as well as other upcoming 6th Street improvement projects including the signalization of the 6th & K-10 interchange ramps.
Project Schedule
Completion of plans: April 2013
Advertise and bidding: May 2013
Construction: Summer 2013
Action Requested
Authorize City Manager to approve purchase order for design services for 6th & George Williams Way signal plans to BG Consultants in the amount of $6500.