Memorandum
City of Lawrence
Public Works
TO: |
David L. Corliss, City Manager
|
FROM: |
David P. Cronin, P.E., Project Engineer
|
CC: |
Charles Soules, P.E., Director of Public Works Shoeb Uddin, P.E., City Engineer
|
Date: |
April 6, 2012
|
RE: |
Project PW1012 - Iowa Street, Harvard Road to Irving Hill Road Additional Engineering Design Services
|
Please include the following item on the City Commission Agenda for consideration at the April 17, 2012 meeting.
Project Description
Bartlett and West Engineers are currently designing plans for the complete reconstruction of Iowa Street from approximately 200' south of Iowa to the Irving Hill overpass. The improvements will include:
Additional Improvements and Design Costs.
On March 9, 2012 the University of Kansas offered to fund construction of two improvements to the project: 1. Extending the second (southernmost) eastbound lane of 15th Street to Engel Road and 2. Extending the 10' wide shared-use path on the south side of Bob Billings Parkway from the current west end of the project (700' west of Iowa) to Crestline Drive. The estimated construction cost of these improvements are $135,780 and $75,000, respectively. The lane extension will be become a right turn only lane onto Engel Road and will improve the function of the 15th & Iowa intersection. The shared-use path extension will provide a continuous pathway from Iowa Street to Crestline Drive.
The proposed engineering design fee for Bartlett & West to prepare plans for the additional work is $15,800. The additional design fee is appropriate for the scope and services Bartlett & West has submitted to complete the work and the city will fund the cost for additional design services.
Project Cost Estimate.
Current Total Construction Cost |
$5.6 million |
Construct Additional eastbound lane of 15th St. to Engel Road |
$136,000 |
Construct Shared-use path extension |
$75,000 |
Total Construction Cost |
$5.8 million
|
Current Engineering and Survey Costs |
$427,745 |
Additional Engineering Design Services |
$15,800 |
Total Engineering Costs
|
$443,545 |
Total Project Cost |
$6.24 million |
|
|
Project Funding.
$1.25 million |
Annual street maintenance fund from City Sales Tax |
$1.0 million |
General Obligation Bonds |
$1.0 million |
Federal Aid Safety Funds |
$3.0 million |
Surface Transportation Program (STP) |
$0.21 million |
KU Participation for additional work |
$6.46 million |
Estimated Total |
Project Schedule
Completion of plans: Fall 2012
Advertise and bidding: December 2012
Construction: 2013
Action Request
Authorize City Manager to execute an Additional Engineering Services Agreement with Bartlett & West for Design Services for additional lane on 15th Street east of Iowa and shared-use path from west project limits to Crestline Drive.