Project Description

Bartlett and West Engineers are currently designing plans for the complete reconstruction of Iowa Street from approximately 200' south of Iowa to the Irving Hill overpass.  The improvements will include:

 

Additional Improvements and Design Costs.

On March 9, 2012 the University of Kansas offered to fund construction of two improvements to the project: 1. Extending the second (southernmost) eastbound lane of 15th Street to Engel Road and 2. Extending the 10' wide shared-use path on the south side of Bob Billings Parkway from the current west end of the project (700' west of Iowa) to Crestline Drive.  The estimated construction cost of these improvements are $135,780 and $75,000, respectively.  The lane extension will be become a right turn only lane onto Engel Road and will improve the function of the 15th & Iowa intersection.  The shared-use path extension will provide a continuous pathway from Iowa Street to Crestline Drive.

 

The proposed engineering design fee for Bartlett & West to prepare plans for the additional work is $15,800.  The additional design fee is appropriate for the scope and services Bartlett & West has submitted to complete the work and the city will fund the cost for additional design services.

 

Project Cost Estimate.

Current Total Construction Cost

$5.6 million

Construct Additional eastbound lane of 15th St. to Engel Road

$136,000

Construct Shared-use path extension

$75,000

Total Construction Cost

$5.8 million

 

Current Engineering and Survey Costs

$427,745

Additional Engineering Design Services

$15,800

Total Engineering Costs

 

$443,545

Total Project Cost

$6.24 million

 

 

Project Funding.

$1.25 million

Annual street maintenance fund from City Sales Tax

$1.0 million

General Obligation Bonds

$1.0 million

Federal Aid Safety Funds

$3.0 million

Surface Transportation Program (STP)

$0.21 million

KU Participation for additional work

$6.46 million

Estimated Total

 

Project Schedule

Completion of plans: Fall 2012

Advertise and bidding: December 2012

Construction: 2013

 

Action Request

Authorize City Manager to execute an Additional Engineering Services Agreement with Bartlett & West for Design Services for additional lane on 15th Street east of Iowa and shared-use path from west project limits to Crestline Drive.