Memorandum

City of Lawrence

Public Works

 

TO:

David L. Corliss

FROM:

Chuck Soules

CC:

Diane Stoddard, Cynthia Wagner, Jonathan Douglass, Casey Toomay, Laura Warner, Ed Mullins

Date:

November 11, 2010

RE:

Resolution 6958:  A Resolution Amending Resolution 6926 and Authorizing the Issuance of General Obligation Bonds for Main Trafficway Improvements

 

The City Commission approved three major reconstruction projects earlier this spring: 

 

KLINK, 6th Street, Iowa Street to Massachusetts Street.  This project includes mill and overlay, right-turn lanes for westbound 6th Street onto northbound Maine and Michigan, striping, waterline relocation, sidewalk and some curb and gutter and base repair. 

 

6th Street from Monterey to Folks Road.  Project includes widening for a center turn lane, mill and overlay, multi-use path, and striping.

 

Bob Billings Parkway, Kasold Drive to Crestline Drive (westbound only).  This project reconstructed the street base, installed underdrains, and placed a 12” asphalt pavement.  The curb and gutter and storm sewer did not require maintenance.

 

Resolution 6891 authorized $1,300,000 for the Bob Billings Parkway project and Resolution 6926 authorized $1,630,000 for the 6th Street projects.  Total construction cost for these projects is $2,491,660.25. 

 

Summary:

 

Bid Received

Included

Anticipated

Change Orders

TOTAL

Bob Billings Parkway

$    667,310.90

$         8,732.54

$      676,043.44

6th Street, KLINK

$ 1,215,161.90

$     (133,813.00)

$   1,117,348.90

6th Street, Folks to Monterey

$    630,112.90

$        68,155.01

$      698,267.91

 

Resolution 6958 amends Resolution 6926 in the amount of $1,692,000 to provide sufficient authority for the 6th Street projects.

 

Action RequestedApprove Resolution 6958 amending Section II of Resolution 6926 and ordering the improvement and authorizing the issuance of General Obligation Bonds for main trafficway improvements.

 

Attachments:  Resolution 6926

                   Resolution 6958