Memorandum
City of Lawrence
Department of Utilities
TO: |
David L. Corliss, City Manager Cynthia Wagner, Assistant City Manager Diane Stoddard, Assistant City Manager
|
FROM: |
Philip E. Ciesielski, Assistant Director of Utilities
|
CC: |
Dave Wagner, Director of Utilities Mike Lawless, Assistant Director of Utilities Beth Krishtalka, Assistant to Director Mark Hegeman, Utilities Operations Superintendent Dave King, Utilities Maintenance Superintendent
|
DATE: |
November 9, 2011 – Updated 11/14/11
|
RE: |
Agenda Item – Set a Bid Date for Bid Number B1156, Project UT0906DS Kaw Water Treatment Plant Large Valve Replacement
|
Please include the following item on the City Commission agenda for consideration at the November 15, 2011 meeting:
Set a bid date of December 6, 2011 for Bid Number B1156, Project UT0906DS Kaw Water Treatment Plant Large Valve Replacement.
Project Details
Through the valve exercising program Utilities Department staff have identified large diameter water distribution system isolation valves at various locations that either do not operate, or operate but do not fully seal. These valves are typically 16” in diameter or larger and on water transmission lines of similar diameters. Because there are fewer connecting watermains, and the operational need to isolate a larger diameter water transmission main is infrequent, the number of valves on large diameter water transmission mains is fewer and they are located at greater distances apart than those on the smaller water mains that make up the bulk of the water distribution system. This makes the need for each available valve to be fully operational critical to allow timely shutdown in the event of an emergency.
The current project scope is designed to address the replacement of four (4) inoperable valves on the Kaw Water Treatment Plant Central Service high service pump discharge transmission mains. These four first tier valves are critical in the event the Kaw WTP needs to be isolated from the transmission system. The project scope replaces four (4) 16” to 24” diameter butterfly valves, 360 linear feet of 24” diameter cast iron transmission main, and two (2) 24” diameter check valves. The two 24” butterfly and check valve combinations date to 1955 and 1958 and are in concrete vaults within the 3rd Street right-of-way. The 24” diameter transmission main dates to 1955 and 1958, and the two 16” butterfly valves in Indiana St. date to 1954 and the early 1900’s.
The concrete vaults will be demolished eliminating a confined space hazard for staff and cleaning up the surface area in the right-of-way. The new butterfly valves will be a direct-bury type with only a standard valve box visible at grade. The two existing check valves will be replaced with a single check valve installed on the high service pump discharge within the Kaw WTP building. The 24” diameter transmission main will be replaced with 36” diameter pipe. Fittings will be installed at the intersection of 3rd and Indiana to facilitate the future extension of the 36” diameter Kaw Water Treatment Plant Transmission Main through North Lawrence and onto Southeast Lawrence. Project map (updated 11/14/11) and photos attached.
Project Timeline
Project Status
BG Consultants have completed final plans and specifications and the project is ready to bid. All proposed work is within the right-of-way and no additional easement acquisition is necessary. Department of Utilities Staff have met with the adjacent property owners along 3rd Street to review the project, and advise them of the construction schedule and access limitations to their property during construction.
Project Schedule*
Advertise for Bid November 16, 2011
Bid Opening December 6, 2011
Award Bid December 13, 2011
Notice to Proceed January 9, 2012
Substantial Completion March 23, 2012
Final Completion April 13, 2012
Project Funding
Funds for project are currently available in both the 2011 Operations and Maintenance and Capital Improvements Project budgets. Department staff will be analyzing the available year end O&M budget between and the award of the bid. The agenda memo requesting the award of the bid will identify the final funding source for the project.
Action Request
Set a bid date of December 6, 2011 for Bid Number B1156, Project UT0906DS Kaw Water Treatment Plant Large Valve Replacement.