Memorandum

City of Lawrence

Public Works

 

TO:

David L. Corliss

FROM:

Chuck Soules

CC:

Diane Stoddard, Cynthia Wagner, Jonathan Douglass, Shoeb Uddin, Mark Thiel, Matt Bond

Date:

November 9, 2011

RE:

2012 CDBG Program Applications

Ridge Court Storm Sewer Improvements

Hazardous Sidewalk Repair

 

The CDBG Program is accepting applications for 2012.  Over the last several years the City has received $500,000 in CDBG funds to install approximately 4 miles of sidewalk.  For 2012 staff would recommend submitting two applications:  Ridge Court Storm Sewer Improvements and Hazardous Sidewalk Repair.

 

Ridge Court Storm Sewer Improvements:

The current storm sewer system in this area is not adequate to handle storms greater than a 5-year storm (20% chance of occurrence per year).  Previous flash flooding in this area caused structure damage to a duplex structure located at 2814 Ridge Court.  As a temporary solution the property was acquired and an undersized detention basis was constructed.  A new 48” diameter HDPE line is proposed to run along the back of the curb on the west side of Ridge Court.  This new line will provide capacity for a 100-year storm (1% chance of the occurrence per year) and will alleviate the local flash flooding.

 

The estimated project cost is $100,000.  City crews could complete this project.  We are requesting $50,000 from the CDBG Program to roughly pay for the materials.

 

Hazardous Sidewalk Repair Program:

This program would identify sidewalks that are in extreme disrepair in low/moderate income areas and replace with new sections of sidewalk.  It costs around $25/linear foot to remove and replace a 5 ft. wide sidewalk.  A single section of sidewalk is typically 4 ft.; therefore, it would cost approximately $100 to replace a typical section.  Low/moderate income families would not be able to afford this cost.  The request would be for $50,000 which could repair about 2,000 ft., or 500 sections of sidewalk.

 

Action Requested:

Authorize staff to submit applications to the 2012 CDBG Program for Ridge Court Storm Sewer Improvements in an amount of $50,000 and Hazardous Sidewalk Repair in an amount of $50,000.

 

Respectfully submitted,

Charles F. Soules, P.E.

Director of Public Works

 

Attachments:  Ridge Court Aerial

                   Hazardous Sidewalk Pictures