Memorandum
City of Lawrence
Public Works
|
TO: |
David L. Corliss |
|
FROM: |
Chuck Soules |
|
CC: |
Diane Stoddard, Cynthia Wagner, Jonathan Douglass, Toni Wheeler, Philip Ciesielski |
|
Date: |
November 2, 2011 – Updated 11/08/11 |
|
RE: |
Fairfield East Addition No. 1, Exchange Place and Fairfield Street Street, Storm Sewer, Waterline Improvements (PW0915) Sanitary Sewer (09S003), Lift Station (09S004) FINAL_MAXIMUM ASSESSMENTS November 8, 2011 Agenda Item |
Project History:
|
July 7, 2009 |
City received a petition for street, water and sanitary sewer improvements |
|
July 14, 2009 |
City approves Resolution 6842 and Resolution 6843 setting out the findings and determination of the Governing Body and ordering the improvements |
|
September 1, 2009 |
City received bids for improvements |
Project Status: The project included the construction of Fairfield and Exchange streets, sidewalks, curb and gutter, water main, sanitary sewer, and a lift station. The projects are complete.
Benefit District: All
costs (100%) are being paid for by the benefit district. The benefit district
includes all property in the Fairfield East Addition (map attached). Property
owners have 30 days from the publication of the ordinance to pay the assessment
in full or the costs will be collected over ten
(10) 20 years with
property taxes.
Action Requested:
Open public hearing and, pending comments, approve Ordinance 8679 and Ordinance 8680 levying the assessments for the costs of the improvements for Fairfield East Addition No. 1.
Respectfully submitted,

Charles F. Soules, P.E.
Director of Public Works
CFS/je
Attachments: Benefit District Map
Final Cost Spreadsheets – street/sewer