  updated as priorities change | 
   | 
   | 
 
 
  |   | 
   
  
   | 
   | 
   | 
    | 
   | 
   | 
 
 
  |   | 
   | 
   | 
   | 
    | 
   | 
   | 
 
 
  |   | 
   | 
   | 
   | 
    | 
   | 
   | 
 
 
  |   | 
   | 
   | 
  Nearly Complete Items | 
   | 
   | 
 
 
  |   | 
   | 
   | 
  Energy Efficiency Projects | 
   | 
   | 
 
 
   
  
   | 
    | 
    | 
    | 
    | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | Manager | 
  Location | 
  Project Description | 
  Cost  | 
  Funding Source | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | Rowan | 
  Burroughs Creek Park | 
  Install new
  playground near 15th street | 
  $28,655 | 
  Private donation PO
  Cut | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | Rowan | 
  Burroughs Creek Park | 
  Swings, tables,
  benches to go near new playground | 
  $8,009 | 
  216 budget - PO Cut | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | Crystal/ Mitch | 
  Oak Hill and Memorial
  Park | 
  Establish rose hedges
  and trees at cemetery entrances | 
  $3,523 | 
  216 and 001-4-4070 -
  PO Cut | 
   | 
   | 
   | 
 
 
  | John | 
  Holcom Park Center | 
  Boiler rehab | 
  $2,809 | 
  216 budget - PO Cut | 
   | 
   | 
   | 
 
 
  | John | 
  South Park Admin
  Office | 
  Install fiber
  switches for new line | 
  $2,587 | 
  216 budget - PO Cut
  by IS | 
   | 
   | 
   | 
 
 
  | John | 
  South Park Admin
  Office | 
  Install new phone
  line with computer fiber | 
  $3,760 | 
  216 budget - PO Cut | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | Lynn | 
  Holcom Park Center | 
  Gym floors refinish
  (includes racquetball court) | 
  $2,209 | 
  001-4-4020 PO Cut | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | Lynn | 
  East Lawrence Center | 
  Gym floors refinish | 
  $2,058 | 
  001-4-4020 PO Cut | 
   | 
   | 
   | 
 
 
  | John | 
  Holcom Park Center | 
  Replace Jace control
  on HVAC system | 
  $2,562 | 
  216 budget - PO Cut | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | John | 
  Clinton Parkway | 
  Replace and grind concrete on bike
  path east of Wakarusa (north side) | 
  $2,900 | 
  216 budget - PO Cut | 
   | 
   | 
   | 
 
 
  | John | 
  Wakarusa & Overland Park | 
  Repair bike paths around the park | 
  $600 | 
  216 budget - PO Cut | 
   | 
   | 
   | 
 
 
  | John | 
  DeVictor Park | 
  Install pad for new
  bench | 
  $404 | 
  216 budget - PO Cut | 
   | 
   | 
 
 
  | Jim | 
  DeVictor Park | 
  Bench for the west
  side of the park along trail (donation) | 
  $936 | 
  Private donation
  /Memorial Tree Fund | 
   | 
   | 
   | 
 
 
  | Crystal/ John | 
  Arboretum | 
  Install new ADA table
  ( $976) and concrete pad ($970) | 
  $1,946 | 
  Private donation
  /Memorial Tree Fund | 
   | 
   | 
   | 
 
 
  | John | 
  Holcom Park Center | 
  Replace basketball
  backboards | 
  $2,200 | 
  216 budget - PO Cut | 
   | 
   | 
   | 
 
 
  | Lynn | 
  Community Building | 
  Repair door openers
  on north doors | 
  $810 | 
  216- proceed with
  Visa | 
   | 
   | 
   | 
 
 
  | John | 
  Carnegie Building | 
  Install ladder to
  roof | 
  $1,281 | 
  216 budget - PO Cut | 
   | 
   | 
   | 
 
 
  | John | 
  Community Building | 
  Install power meter
  on building automated control system | 
  $1,600 | 
  216 budget - PO Cut | 
   | 
   | 
   | 
 
 
  | Mitch | 
  Memorial Park
  Cemetery | 
  Replace damaged grave
  markers | 
  $5,000 | 
  Memorial Park
  Reserve Fund - PO Cut | 
   | 
 
 
  | John/ Crystal | 
  Downtown | 
  Repair green hydrants
  that are leaking | 
  $900 | 
  Blanket PO - Proceed | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | Mitch | 
  Memorial Park Oak
  Hill  | 
  Scan cemetery files | 
  $1,500 | 
  001-4 budget PO Cut | 
   | 
   | 
   | 
 
 
  | Darin | 
  District #1 | 
  Misc sodding projects | 
  $5,280 | 
  EBGC budget and 216
  - PO Cut | 
   | 
   | 
   | 
 
 
  | Darin | 
  Eagle Bend Golf
  Course | 
  Change band width on
  irrigation radio controllers (FCC required) | 
  $14,900 | 
  PO Cut - Golf
  Course  | 
   | 
   | 
   | 
 
 
  | John | 
  Youth Sports
  Complex  | 
  Install additional
  dirt to level football field #1 | 
  $1,500 | 
  216 budget - PO Cut | 
   | 
   | 
   | 
 
 
  | Lynn | 
  East Lawrence Center | 
  Resurface roof | 
  $81,595 | 
  2011 Sales Tax - PO
  Cut | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | John | 
  Youth Sports
  Complex  | 
  New restroom building
  south of football fields includes utilities to site | 
  $67,490 | 
  2011 Sales Tax - PO
  Cut | 
   | 
   | 
   | 
 
 
  | John | 
  Admin Office | 
  Remove old walls to
  allow for new offices | 
  $3,500 | 
  2011 Sales Tax - PO
  Cut | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | John | 
  Holcom Park Center | 
  Repair basketball
  goal supports on main court | 
  $5,453 | 
  2011 Sales Tax
  Change Order Requested | 
   | 
   | 
   | 
 
 
  | John | 
  Downtown | 
  Tree grate Install | 
  $9,777 | 
  2011 Sales Tax - PO
  Cut | 
   | 
   | 
   | 
 
 
  | John | 
  South Park Center /
  CB | 
  Install new computer
  fiber cable in conduit | 
  $5,875 | 
  2011 Sales Tax - PO
  Cut | 
   | 
   | 
   | 
 
 
   
  
   | 
    | 
    | 
    | 
    | 
   | 
   | 
 
 
  | John | 
  South Park Admin
  Office | 
  HVAC work for Phase I
  of the building | 
  $14,000 | 
  2011 Sales Tax | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | John | 
  South Park Admin
  Office | 
  Electrical upgrade
  and rewire phase I | 
  $14,000 | 
  2011 Sales Tax | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | Lynn | 
  South Park Admin
  Office | 
  Flooring Phase I | 
  $12,500 | 
  2011 Sales Tax | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | John | 
  South Park Admin
  Office | 
  Plumbing for new
  restroom | 
  $12,000 | 
  2011 Sales Tax | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | Rowan | 
  South Park Admin
  Office | 
  Wall construction and
  doors | 
  $8,500 | 
  2011 Sales Tax | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | Lynn | 
  South Park Admin
  Office | 
  Glass door changes | 
  $6,300 | 
  2011 Sales Tax | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | John | 
  South Park Admin
  Office | 
  Painting | 
  $5,000 | 
  2011 Sales Tax | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | Crystal | 
  South Park Admin
  Office | 
  Landscaping | 
  $2,500 | 
  2011 Sales Tax | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | John | 
  South Park Admin
  Office | 
  Concrete sidewalk | 
  $4,500 | 
  2011 Sales Tax | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | Lynn | 
  South Park Admin
  Office | 
  Front entrance cover | 
  $3,500 | 
  2011 Sales Tax | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | Mark | 
  Broken Arrow Park | 
  Overlay parking lot | 
  $15,000 | 
  2011 Sales Tax -
  Public Works to do the work?? | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | Lynn | 
  Holcom Park Center | 
  Install new flooring
  in lobby  | 
  $15,000 | 
  2011 Sales Tax | 
   | 
   | 
   | 
 
 
  | Jimmy | 
  Indoor Aquatic Center | 
  Replace 21 Competitor
  lap lane lines 75’ x 6” | 
  $13,000 | 
  2011 Sales Tax | 
   | 
   | 
   | 
 
 
  | Lynn | 
  Outdoor Aquatic
  Center | 
  Resurface exterior of
  blue slide | 
  $4,500 | 
  2011 Sales Tax | 
   | 
   | 
   | 
 
 
  | Mitch | 
  Oak Hill Cemetery | 
  Remove old holding
  vault | 
  $3,200 | 
  2011 Sales Tax | 
   | 
   | 
   | 
 
 
  |   | 
    | 
  Sales Tax Uncommitted
  Projects Funds | 
  $6,717 | 
  2011 Sales Tax | 
   | 
   | 
 
 
  |   | 
    | 
  Total funding sales
  tax funding available for 2011 | 
  #REF! | 
    | 
   | 
   | 
 
 
  |   | 
    | 
    | 
    | 
    | 
   | 
   | 
 
 
  | Mark | 
  Outdoor Pool | 
  Paint Pool / concrete
  repairs / slide refinish   approved for
  $100,000 total | 
    | 
  Bond Money 2011-2012 | 
   | 
   | 
   | 
 
 
  |   | 
    | 
  Pool Painting | 
  $57,000 | 
  Bond Money 2011-2012 | 
   | 
   | 
   | 
 
 
  |   | 
    | 
  Bathhouse Painting | 
  $14,000 | 
  Bond Money 2011-2012 | 
   | 
   | 
   | 
 
 
  |   | 
    | 
  Apply wood stain and
  sealer to other non-painted wood surfaces | 
  $3,600 | 
  Bond Money 2011-2012 | 
   | 
   | 
   | 
 
 
  |   | 
    | 
  Resurface exterior
  of blue slide | 
  $4,800 | 
  Bond Money 2011-2012 | 
   | 
   | 
   | 
 
 
  | Mark  | 
  Deerfield Park  | 
  Replace concrete
  courts / fencing / playground | 
  $150,000 | 
  Bond Money 2011-2012 | 
   | 
   | 
   | 
   | 
 
 
  | Mark | 
  Centennial Park | 
  Skate Park
  Improvements | 
  $125,000 | 
  Bond Money 2011-2012 | 
   | 
   | 
   | 
 
 
  | John | 
  Youth Sports
  Complex  | 
  Install lights on
  diamonds 5-8 | 
  $20,000 | 
  216 budget | 
   | 
   | 
   | 
 
 
  | Rowan/ John | 
  Burroughs Creek Park | 
  Install containment
  boarder and surfacing under new playground | 
  $7,000 | 
  216 budget | 
   | 
   | 
   | 
 
 
  | Crystal /
  Darin | 
  EBGC | 
  Install 25-30 new
  trees on golf course this fall  | 
  $2,000 | 
  216 budget | 
   | 
   | 
   | 
 
 
  | Lynn | 
  Community Building | 
  Repair overhang on
  the front of the building | 
  $2,300 | 
  216 budget | 
   | 
   | 
   | 
 
 
  | Lynn | 
  Holcom Park Center | 
  Repair leaking sky
  light | 
  $2,500 | 
  216 budget | 
   | 
   | 
   | 
 
 
  | Darin | 
  Youth Sports
  Complex  | 
  Laser level &
  irrigation upgrades for football field #1 | 
  $2,500 | 
  216 budget | 
   | 
   | 
   | 
 
 
  | John | 
  Holcom Concession | 
  Exterior paint
  touch-up | 
  $1,500 | 
  216 budget | 
   | 
   | 
   | 
 
 
  | Darin | 
  Holcom Complex | 
  Replace batting cage
  net | 
  $1,500 | 
  216 budget | 
   | 
   | 
   | 
 
 
  | Mitch | 
  Lyons | 
  Laser level infield
  on field #2 | 
  $1,200 | 
  216 budget | 
   | 
   | 
   | 
 
 
  | Lynn | 
  South Park Wading
  Pool | 
  Investigate plumbing
  backwash drain to sanitary sewer pit | 
  $1,000 | 
  216 budget | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | Lynn | 
  Holcom Park Center | 
  Replace window in
  game room | 
  $305 | 
  216 budget | 
  $41,805 | 
  Total 216 budget | 
   | 
 
 
  | Lynn | 
  Outdoor Aquatic
  Center | 
  Resurface diving
  boards | 
  $2,200 | 
  211-4-4180 | 
   | 
   | 
   | 
 
 
  | Tim/ Lynn | 
  Carnegie Building | 
  Curtain to hide
  display during reservation | 
  $10,000 | 
  211-4-4190-2325 | 
   | 
   | 
   | 
 
 
  | Jim | 
  North Kasold Islands | 
  Install trees and
  landscaping on islands after asphalt | 
  $12,000 | 
  Public Works Funding | 
   | 
   | 
   | 
 
 
  | John | 
  Holcom, Hobbs, Broken
  Arrow | 
  Replace old wood
  poles on ball diamond light | 
  $40,000 | 
  ???? | 
   | 
   | 
   | 
 
 
   
  
   | 
    | 
    | 
    | 
    | 
   | 
   | 
 
 
  | Priority | 
    | 
    | 
    | 
    | 
   | 
   | 
 
 
  | 1 | 
  Hobbs Park | 
  Replace existing ball
  diamond lights with energy efficient lighting | 
  $75,000 | 
    | 
   | 
   | 
   | 
 
 
  | 2 | 
  Broken Arrow Park | 
  Replace existing ball
  diamond lights with energy efficient lighting | 
  $75,000 | 
    | 
   | 
   | 
   | 
 
 
  | 3 | 
  South Park Admin
  Office | 
  Complete the
  renovation of new Parks & Recreation office (2012) | 
  $20,000 | 
    | 
   | 
   | 
   | 
 
 
  | 4 | 
  Clinton Lake Softball
  Complex | 
  Replace batting cage
  nets and upgrade feeding tubes | 
  $30,000 | 
    | 
   | 
   | 
   | 
 
 
  | 5 | 
  Holcom Park Center | 
  Install new floor in
  Bly Room | 
  $15,000 | 
    | 
   | 
   | 
   | 
 
 
  | 6 | 
  Prairie Park / Mary's
  Lake | 
  Installation of
  improved restroom near Mary's Lake | 
  $50,000 | 
    | 
   | 
   | 
   | 
 
 
  | 7 | 
  Holcom Park Center | 
  Repair / replace
  Kawall skylight in Gym | 
  $50,000 | 
    | 
   | 
   | 
   | 
 
 
  | 8 | 
  Watson Park | 
  Install rubberized
  play surface under playground  | 
  $32,000 | 
    | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | 9 | 
  Community Building | 
  Clean and tuck point
  exterior of building | 
  $30,000 | 
    | 
   | 
   | 
   | 
 
 
  | 10 | 
  Holcom Park | 
  Install rubberized
  play surface under playground | 
  $30,000 | 
    | 
   | 
   | 
   | 
 
 
  | 11 | 
  Carnegie Building | 
  Resurface roof on old
  part of building | 
  $45,000 | 
    | 
   | 
   | 
   | 
   | 
 
 
  | 12 | 
  Broken Arrow Park | 
  Replace concrete
  floor in main shelter | 
  $13,000 | 
    | 
   | 
   | 
   | 
 
 
  | 13 | 
  Downtown | 
  Continue tree grate
  installation program | 
  $15,000 | 
    | 
   | 
   | 
   | 
 
 
  | 14 | 
  Veterans Park | 
  Replace playground | 
  $30,000 | 
    | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | 15 | 
  Eagle Bend Golf
  Course | 
  Install new
  electrical system to allow for use of electric carts | 
  $50,000 | 
    | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | 16 | 
  Clinton Park | 
  Clean and tuck point
  historic stone wall | 
  $30,000 | 
    | 
   | 
   | 
   | 
 
 
  | 17 | 
  City Entrances -
  Turnpike | 
  Landscape & sign
  on new round-a-bouts | 
  $50,000 | 
    | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | 18 | 
  Broken Arrow Park | 
  Replace park
  Restroom  | 
  $75,000 | 
    | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
 
 
  | 19 | 
  Centennial Park | 
  Install rubberized
  play surface under playground | 
  $40,000 | 
    | 
   | 
   | 
   | 
 
 
  | 20 | 
  Memorial Park
  Cemetery | 
  Replace curb and
  gutter along streets to prevent erosion areas | 
  $10,000 | 
    | 
   | 
   | 
   | 
 
 
  |   | 
    | 
    | 
  $765,000 | 
    | 
   | 
   | 
 
 
  |   | 
    | 
    | 
    | 
    | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
   | 
   | 
 
 
   | 
    | 
   | 
   | 
 
 
 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   | 
   |