Memorandum
City of Lawrence
Utilities Department
TO: |
David L. Corliss – City Manager Diane Stoddard - Assistant City Manager Cynthia Wagner - Assistant City Manager |
FROM: CC: |
Dave Wagner – Director of Utilities Mike Lawless – Asst. Director of Utilities |
|
Philip Ciesielski – Asst. Director of Utilities Beth Frailey Krishtalka – Assistant to Director |
Date: |
May 20, 2011 |
RE: |
Information Requested from the May 17th Budget Study Session |
|
|
In response to the City Commissioners’ questions concerning Utilities staffing, technology and volume of water treated, and efficiencies at the May 17th Study Session the following information is provided. Time savings as a result of increasing efficiencies realized due to improved work practices and automation have been redirected to three major areas: 1) Maintaining and operating expanded infrastructure, 2) Addressing previously deferred maintenance of infrastructure, 3) Consolidating or taking over services previously performed by other departments. A brief discussion of each follows:
Maintaining and Operating Expanded Infrastructure
Generally reduced water production on an average day basis does not significantly reduce workload. The number of facilities, their size, and peak capacities are more of a driver of staffing needs and workload. Overall, the infrastructure the department is responsible for has, and continues, to increase (see table) and therefore the workload and resource needs have also increased, even though average day water production is lower. When efficiencies have reduced workload, much of that has been redirected to respond to these increased needs.
In addition to the above, there have been two major facility expansions that have come on line since 2004. The Clinton Water Treatment Plant increased from 10 million gallons per day (MGD) to 22.5 MGD with the $20 million expansion project that came on line in 2009. From 1998-2004 the Wastewater Treatment Plant was expanded at a cost of $59 million for increased capacity and treatment quality. Due to efficiencies realized with the installation of enhanced automation with both these major projects, the level of plant operator staffing did not change. However, there were, and are, increases in maintenance and control system maintenance demands, as well as consumption of commodities, such as electricity and chemicals, that are used to increase the quality as well as the peak quantity of treatment at both of these facilities.
Addressing Deferred Infrastructure Maintenance and Improving Services
As much as possible manpower and resources have been redirected to increase the level of maintenance and rehabilitation of infrastructure and improve services.
Programs such as the 10-year TV inspection, 4-year section cleaning, root control, CIPP, and targeted preventative maintenance locations have been in place on the sewer collection system since 1998 and have been continued or expanded. A reduction in the number of the customer service calls is one of the benefits from these types of programs as seen on the attached graph. With continued emphasis on these types of programs on the water distribution system, the department believes similar benefits will result.
Since 2006, the group has designed automated systems for 12 wastewater pump stations, the expansion of the Clinton WTP, construction of the Stoneridge water tower, and replacement of systems at all 5 existing water towers. The group is currently replacing all systems at the Kaw WTP, working on the North Final MCC Replacement, and Anaerobic Digester Expansion projects at the WWTP.
By performing these tasks with in-house staff, the department not only experienced a substantial cost savings (in excess of $1,000,000 on these projects alone) but we are now self sufficient in maintaining and improving these systems without the cost of third party vendors. From 2007 to 2009, the department spent more than $50,000 for third party contractors to trouble shoot and repair their SCADA equipment.
Work Previously Performed by Other Departments
The department has taken on expanded responsibilities since 2007. These include:
Since 2007, the number of full-time employees (FTE) funded by the water and wastewater rates has decreased by 5 in Utilities and increased by 0.5 in the General Fund for a net decrease of 4.5. See table below.
As a priority, the department continues to reinvest in our infrastructure whenever possible. While there are no CIP projects in the 2011 budget that focus on infrastructure maintenance, the 2011 and prior years’ Operations and Maintenance Budgets have and do provide funding for some level of infrastructure maintenance. While not at the magnitude of a major CIP effort, it does provide funding to sustain programs for maintenance and rehabilitation of much of the above ground and treatment process mechanical systems.