Memorandum

City of Lawrence

Planning & Development Services

 

TO:

David L. Corliss, City Manager

 

FROM:

Barry Walthall, Building Codes Administrator

 

CC:

Scott McCullough, Planning & Development Services Director

 

Date:

May 3, 2011

 

RE:

April 2011 Monthly Permit Report

 

The Building Safety Division issued 196 building permits in April, with total construction for the month valued at $5,536,213.  Total permit fees assessed for the month were $53,111.  Monthly and year to date comparisons to previous years will be tracked throughout 2011 in the following table:

 

 

2011

2010

2009

2008

Total Permit Valuation, April

$5,536,213

$12,605,541

$6,482,254

$19,402,345

Total Permit Valuation, YTD

$19,479,026

$28,772,687

$28,256,184

$37,809,296

Permit Fees Assessed, April

$53,111

$41,877

$47,977

$77,670

Permit Fees Assessed, YTD

$171,261

$168,466

$194,760

$205,367

 

There were 14 permits issued for new residential construction in April, all of which were for single-family dwellings.  Permits were issued for 29 new residential projects in April last year, 26 for single-family dwellings and three for duplexes.  Monthly and year-to-date statistics for total permits issued and new residential projects will be tracked in the following table, similar to permit valuation and fees:

 

 

2011

2010

2009

2008

Total Permits, April

196

155

169

189

Total Permits, YTD

652

607

565

626

Single-Family/Duplex Permits, April (# of units)

14(14)

8(8)

6(6)

14(14)

Single-Family/Duplex Permits, YTD (# of units)

35(37)

56(59)

21(23)

27(27)

Multi-Family Permits, April (# of units)

0(0)

0(0)

2(16)

1(4)

Multi-Family Permits, YTD (# of units)

10(63)

0(0)

15(172)

2(7)

Total Residential Permits, YTD (# of units)

45(100)

56(59)

36(195)

29(36)

 

The highest valued project for the month was for a building remodel and building systems upgrades at Plastikon Industries, 3780 Greenway Circle, valued at $800,000.  There was one public project, for replacement of radiology equipment at LMH, 325 Maine, valued at $99,000.

 

Top Projects for 2011:

Rank

1

Construction Valuation

$2,117,709

Project Description

Crossgate Casitas, 2451 Crossgate Drive

2

$2,000,000

Hy-Vee Renovation, 3405 Clinton Parkway

3

$1,340,000

Northwinds Apartments, 200 N Michigan Street

4

$800,000

Plastikon Industries, 3780 Greenway Circle