This preliminary construction cost estimate assumes 18-20 acres of land to be used for the memorial. The cost of the land and permits are not added into this estimate.
This memorial project has a preliminary construction cost of the following:
Land Construction:
Land Civil work (parking, drainage, utilities, etc….) $3,000,000.00
Landscaping (vegetation, irrigation, etc…) $900,000.00
Building Construction:
Entry way ((2) 130’ towers, Large Flag, Chimes, Military Seals, etc... $1,000,000.00
Exhibit/Theater Building (11,000+ sf (includes exhibit support & telecomm)) $6,000,000.00
Admin./Research & Library/Outreach Building (7,000+ sf) $4,000,000.00
Workshop/Maintenance/Mechanical Systems Support Building (3,500+ sf) $3,000,000.00
Memorial (Star configuration, walls, Flags, State names on granite,
faced walls, Plague, Pathways/walks, etc….) 5,000,0000.00
Sub Total: $22,900,000.00
10% for construction contingency $3,435,000.00
Preliminary Total Construction Cost Estimate………………………………………………..……$26,355,000.00
Above total includes costs for alternative energy (solar and wind) and geothermal heating and cooling for this project.