Reconstruction of Iowa Street, from 200’ South of Harvard to Irving Hill Overpass

February 8, 2011 City Commission Agenda Item

 

Please include the following item on the City Commission agenda for consideration at the February 8, 2011 meeting:  Authorize the City Manager to execute an Engineering Services Agreement in the amount of $394,170 with Bartlett & West Engineers for the design of the Iowa Street Reconstruction, Project No. PW1012.

 

Project History

3/9/10

Staff presented condition of Iowa to City Commission; redistribution of street maintenance program funding

3/29/10

Public meeting regarding Iowa Street

4/27/10

City Commission determines to reconstruct Iowa from Harvard to Bob Billings Parkway with left turn lane

5/25/10

Request for Qualifications for engineering design; Resolution 6889 authorizing issuance of bonds

7/13/10

Recommendation to City Commission to negotiate with Bartlett & West for engineering services

12/7/10

Report to City Commission on options and scope of work, including sidewalks/multi-use path, intersection improvements, project limits

12/7/10

City/State Agreement for STP funds in an amount of $3 million

 

Project DetailsThis project includes the complete reconstruction of Iowa Street from approximately 200’ south of Harvard to the Irving Hill overpass.  The improvements will include:

  • Two lanes north and southbound at 11’ wide
  • 12’ wide center turn lane
  • 6’ sidewalk on the west side
  • 6’ sidewalk on the east side from Harvard to University, and from 15th St. to the Irving Hill overpass
  • Intersection improvements at Bob Billings Parkway (15th Street) to include dedicated right turn lanes in all directions, dual left turn lanes on north and southbound Iowa
  • Project limits on Bob Billings Parkway west approximately 600’, including a 10’ sidewalk
  • BBP/15th Street east of Iowa will be milled and overlaid
  • Full depth pavement removal and replacement, curb and gutter, subgrade preparation, storm sewer and drainage improvements

 

Project Cost Estimate.

Iowa Street (from Harvard to Irving Hill)

$4.5 million

Southbound right turn lane

$100,000

West leg of the intersection

$600,000

East leg of the intersection

$250,000

Traffic signal pole relocation / adjustment

$150,000

     Total Construction Cost

$5.6 million

Engineering and Survey

$427,745

     Approximate Total Cost

$6.028 million

 

Project Funding.

$1.25 million

Annual street maintenance fund from City Sales Tax

$1.0 million

General Obligation Bonds

$1.0 million

Federal Aid Safety Funds

$3.0 million

Surface Transportation Program (STP)

$6.25 million

Estimated Total

 

Engineering Proposal.

On July 13, 2011 City Commission authorized staff to negotiate an Engineering Services Contract with Bartlett & West for the Iowa Street project (memo attached).  Public Works staff and Bartlett & West have thoroughly reviewed the scope of services for the project.  Since this project has $4 million in Federal funds ($3 million STP and $1 million Safety) and is a state highway the project will be let by KDOT and KDOT will have oversight of the design.

 

Attached is the Scope of Services including survey, horizontal/vertical alignment, traffic control, typical section, plan/profile, utility locates, stormwater drainage design/analysis, erosion control plan, detail sheets, signal timing, earthwork quantities and estimates for field check, and final plans. 

 

The proposed engineering design service fee for Bartlett & West to prepare a complete set of plans and specifications, including KDOT review and approval, is $394,170.  This fee also includes a public information meeting and easement services (right-of-way strip maps and descriptions) not included in the Design Fee Guidelines.  Evaluating this fee to the Design Fee Guidelines would include:

Estimated Construction Cost

$5.6 million

Fee Proposal

$394,170 plus $33,575 for already contracted survey

Total Engineering Services

$427,745 (7.6%)

Based on the complexities of this project and state review/oversight the fee is appropriate for the scope of services and in accordance with the Design Fee Guidelines.

 

The City will hire a geotechnical firm under separate agreement to conduct soil/base investigation/analysis.

 

Project Status.  We would like to bid this project in 2012.  This spring staff will be working with the University Neighborhood to develop a traffic calming plan. 

 

Action Requested.  Authorize City Manager to execute an Engineering Service Agreement with Bartlett & West for Design Services for Iowa Street Reconstruction, Project PW1012, in an amount of $394,170.

 

Respectfully submitted,