Summary of Results by Bond Issuance
Construction Costs
T-Hangars $870,000 $43,500 per T-Hangar
Site Prep $409,075
Admin & Engineering $69,000
Construction Svcs $30,000
Total Construction Costs $1,378,075
Revenue Returns
Issue Year 2011
Rental Rate $255 per month
Escalation 1% rent rate escalates 1% per year, starting in Year 3, reflecting occasional lease renewals and
new lease agreements.
Occupancy 95% 95% occupancy achieved in Year 3 and maintained thereafter.
Revenues $1,990,706
Bond Term Interest Rate Interest Costs Net Subsidy* Average City Subsidy, First 12 Years Breakeven Year Present Value, 6% Discount** Present Value, 5% Discount**
12 Year 4.00% $433,930 ($103,700) ($87,150) 2031 ($67,493) $31,221
20 Year 4.77% $901,588 $363,958 ($47,103) 2035 ($95,569) ($38,675)
30 Year 5.11% $1,479,114 $941,483 ($27,175) 2036 ($95,559) ($78,796)
Bonds valued over a 30 year period
*Represents total payments from other hangars needed to pay principal and interest on new debt.
   A negative number means that the new hangars receive no subsidy to pay off principal and interest.
** Present value is revenue from all T-Hangars less ongoing expenses for all T-Hangars, less debt payments on new T-Hangars.
Recommendation:
*12 Year bond
*Policy: no T-Hangar can subsidize additional T-Hangars until the revenue received from the new t-hangars
   has fully paid off the principal and interest on construction.