Public Works Projects

Project

Percentage fee

Estimated Construction Budget

Airport Improvements

12%

$   443,678.00

19th and Louisiana Geometric Improvements

11%

$   732,779.00

Kasold, 23rd Street to 31st Street

10.6%

$ 4,300,000.00

StoneRidge Drive, 6th Street to Silverstone Drive

8%

$   385,412.00

25th Terrace, O-Connel Road to Franklin Road

8%

$2,492,823.00

Overland Drive, Queens Road to StoneRidge Drive

5%

$2,138,582.00

GWW, 6th Street to Overland Drive

5%

$2,100,000.00

GWW, Overland Drive to N. City Limits

5%

$1,765,000.00

6th Street and Congressional Drive, Intersection, Traffic and Signal Improvements.

5%

$   274,648.00

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Utilities Projects- Facilities

 

Project

Percentage fee

Estimated Construction Budget

Well Field & N. Final Electrical

15.96%

$ 284,000.00

KAW WTP LSPS2 Pump Replacement

15.27%

$   562,300.00

Sanitary Sewer Pump Station Rehab

10.87%

$ 2,499,800.00

N. Lawrence PS1, PS2 & PS3

10.76%

$ 1,900,000.00

Pump Station PS25

10.50%

$ 3,038,400.00

Pump Station PS46 Riverside Business Park

8.77%

$ 894,242.00

Anaerobic Digester Improvement

8.64%

$ 4,500,000.00

WWTP Expansion

7.23%

$ 37,910,000.00

Clinton WTP Expansion

6.68%

$ 15,460,000.00

KSW WTP Brick Rehab Year 1

6.46%

$   400,000.00

KAW WTP Brick Rehab Year 2

6.08%

$   425,000.00

KAW WTP Hypo Chlorite

5.96%

$   450,000.00

KAW WTP Roof Replacement and Rehab

5.83%

$   160,000.00

WWTP Admin Building HVAC

4.72%

$   375,000.00

KAW WTP High Service Pump Replacement

3.99%

$   350,000.00

StoneRidge Drive Elevated Tank

2.90%

$ 3,200,000.00

 

 

Utilities Projects – Linear

 

Project

Percentage fee

Estimated Construction Budget

  N Iowa & I70 Sewer and Water Relocate Phase II

13.96%

$344,504.40

 Kaw WTP Transmission Main

11.95%

$6,500,000.00

 Bauer Brook Estates Sewer/Water BD’s

11.34%

$535,000.00

 New Hampshire & Delaware Area Sanitary Sewer

10.66%

$578,000.00

 6th & Indiana/17th & Mass Sanitary Sewer

9.21%

$1,655,967.17

 Airport Area Sanitary Sewer

8.56%

$1,186,354.00

 Watermain Rehab Phase I – Iowa

7.70%

$1,500,000

 Airport Area Watermain

7.52%

$1,100,000.00

 N Iowa & I70 Sewer Relocate Phase I

6.28%

$84,337.68

 2005 Downtown Watermain

6.12%

$947,676.73

 2006 Downtown Watermain

5.54%

$1,772,429.67

 24th & Crossgate and Wakarusa & Harvard Sanitary

5.41%

$750,000.00

14th & Tennessee Sanitary Sewer

4.78%

$250,000.00

 Alvamar Area Sanitary Sewer

4.48%

$1,300,000.00

 2007 Downtown Watermain

4.12%