Memorandum
City of Lawrence
Public Works
TO: |
David L. Corliss |
FROM: |
Chuck Soules |
Date: |
September 22, 2010 |
CC: |
Cynthia Boecker, Diane Stoddard, Jonathan Douglass |
RE: |
31st Street – Haskell Avenue to O’Connell Road Street, Storm Sewer, Waterline Improvements KDOT Project No. 23 U-2117-01 – City Project No. 18-CP7-507(S) WETLAND DELINEATION & SURVEY September 28, 2010 Agenda Item |
Please include the following item on the September 28, 2010 City Commission Agenda:
Project History.
6/15/06 |
City submitted a Request for Construction Project to initiate the project |
4/24/07 |
City Commission approved consultant selection process |
8/23/07 |
City Commission approves consultant selection of Wilson & Company, Inc. |
11/1/07 |
Study Session with City Commission; Wilson & Co. 8/30/07 improvements memo |
2/12/08 |
Approved Scope of Services with Wilson & Co. |
3/24/08 |
Briefing of Board of County Commission |
4/7/08 |
Formal letter from Board of County Commissioners to City Commission to expand scope of project to Route 1057 |
5/29/08 |
Met with City and County staff to discuss project |
6/13/08 |
Steering Committee Meeting |
7/11/08 |
Steering Committee Meeting |
7/25/08 |
Met with O’Connell Youth Ranch Board of Representatives |
9/29/08 |
Public meeting at fairgrounds |
10/20/08 |
Met with KDOT/FHWA regarding environmental process and project responsibilities |
10/31/08 |
Steering Committee Meeting |
11/10/08 |
City/County Commission Study Session |
9/20/10 |
Supplemental Agreement #2 – Wetland Delineation |
Project Status.
The City received Federal funds for the preliminary design and right-of-way acquisition for the referenced project. One of the requirements of using Federal funds is that plans need to be developed to the “field check” stage prior to acquiring right-of-way. Plans need to be sufficiently designed to know what the property needs are before acquisition begins.
The State has determined that wetlands may exist and are requiring the delineation of any areas that may be disturbed. The field check plans need to include this determination. This will be the final step to submitting field check plans to KDOT. All costs are being paid from the Federal Appropriation ($792,000).
Action Requested:
Authorize Mayor to sign Supplemental Agreement No. 2 with Wilson & Company for the wetland delineation and survey in an amount not to exceed $15,750.