Memorandum
City of Lawrence
Utilities Department
TO: |
David L. Corliss – City Manager Cynthia Wagner - Assistant City Manager Diane Stoddard - Assistant City Manager |
FROM: |
John Bertrand – Project Engineer |
CC: |
Dave Wagner – Director of Utilities Philip Ciesielski – Asst. Director of Utilities Mike Lawless – Asst. Director of Utilities Beth Frailey Krishtalka – Assistant to Director Mark Hegeman – Utilities Operations Superintendent |
Date: |
September 01, 2010 |
RE: |
September 07, 2010 Agenda Item – Set a Bid Date of September 28, 2010 for Bid No. B1049 Project UT1002DS, Indiana Street Waterline Crossing at 6th Street. |
Please include the following item on the City Commission Agenda for consideration at the September 07, 2010 meeting:
Set a Bid Date of September 28, 2010 for Bid No. B1049 Project UT1002DS, Indiana Street Waterline Crossing at 6th Street.
Project Details/History
The existing 14” cast iron water transmission main currently in service on Indiana Street from W. 3rd Street south to W. 8th Street was constructed in 1886. This water main is part of the transmission system to provide water to the Harper Street water tank and to areas on the south and east side of Lawrence. Based on the age and maintenance history, Utilities staff are constructing a new 12” ductile iron water main as a part of the 2010 in-house water main replacement program.
This section of the project pertains to the boring of the 12” ductile iron water main in 20” steel casing on Indiana Street crossing 6th Street (see Exhibit). 6th Street is KDOT HWY US-40 Right of Way. BG Consultants were tasked with developing plans, specifications, obtaining a KDOT permit and a construction estimate.
Project Status:
BG Consultants have completed the construction plans and specifications for the proposed crossing and the project is ready to bid. The necessary KDOT permit for the construction of the project has been received.
Project Schedule
Set Bid Date September 07, 2010
Pre-Bid Meeting September 20, 2010
Bid Opening September 28, 2010
Award Bid October 05, 2010
Notice to Proceed October 25, 2010
Project Completion November 24, 2010
Project Funding:
The project will be funded from the 2010 Utilities Department Operations and Maintenance Budget for Water Distribution.
Recommendation
Set a Bid Date of September 28, 2010 for Bid No. B1049 Project UT1002DS, Indiana Street Waterline Crossing at 6th Street.
Thank you for your assistance. Please advise if you have any questions.