Memorandum

City of Lawrence

Utilities Department

 

TO:

David L. Corliss – City Manager

Cynthia Wagner - Assistant City Manager

Diane Stoddard - Assistant City Manager

FROM:

John Shutak – Utilities Engineer

CC:

Dave Wagner – Director of Utilities

Philip Ciesielski – Asst. Director of Utilities

Mike Lawless – Asst. Director of Utilities

Beth Frailey Krishtalka – Assistant to Director

Mark Hegeman – Utilities Operations Superintendent

Date:

August 30, 2010

RE:

September 07, 2010 agenda item – set a Bid Date of September 28, 2010 for Bid No. B1050 Project UT0905CS, sanitary sewer main replacement for the 1100 block of Delaware Street, the 1500 block New Hampshire Street and the 700 block of Michigan Street.

 

Please include the following item on the City Commission Agenda for consideration at the September 07, 2010 meeting:

Set a bid date of September 28, 2010 for Bid No. B1050 Project UT0905CS, sanitary sewer main replacement for the 1100 block of Delaware Street, the 1500 block New Hampshire Street and the 700 block of Michigan Street.

 

Project Details

Department of Utilities staff continuously evaluates the condition of the wastewater collection system as part of the regular maintenance program. Based on efforts to perform video inspection of the existing lines servicing the 1100 block of Delaware Street and the 1500 block of New Hampshire Street, it has become apparent that the sanitary sewer lines are in a deteriorated state and require replacement. The sewer lines are cracked and collapsed to the point a video inspection was not possible. Department of Utilities staff have repaired the City main or responded to service backups five (5) times in the past year for the existing line servicing the 1100 block of Delaware and six (6) times in the past year for the existing line servicing the 1500 block of New Hampshire.

 

The existing sewer lines servicing both the 1100 block of Delaware Street and the 1500 block of New Hampshire consist of 6 inch diameter vitrified clay pipe and have been in service for over 70 years.

 

The existing sewer lines servicing the 700 block of Michigan were identified in the 2003 Wastewater Master Plan as project #CS04-08. This area has been a source of sanitary overflow and backup problems during high rainfall events. Utilities staff placed flow monitoring equipment at select manhole locations to identify the problem areas. Phase 1 of the project, completed in January 2008 as part of project UT0702CS, involved installation of approximately 2500 feet of cured-in-place-pipe (CIPP) liner. Phase 2 of project UT0702CS involves the installation of approximately 640 feet of cured-in-place-pipe (CIPP) liner in the East right-of-way along Michigan Street and approximately 217 linear feet of 12 and 8 inch diameter PVC sanitary sewer pipe. Phase 2 of project UT0702CS will be completed as part of project UT0905CS.


The total project will include the installation of approximately 1,080 linear feet of sanitary sewer line servicing the 1100 block of Delaware Street, approximately 630 linear feet of sanitary sewer line servicing the 1500 block of New Hampshire Street, and approximately 217 linear feet of sanitary sewer line and 640 feet of cured in place pipe (CIPP) servicing the 700 block of Michigan Street as identified on the project maps.

 

Project History


Project Status:

BG Consultants have completed the construction plans and specifications for the proposed improvements. All easements and permits necessary for the construction of the project have been acquired as of July 30, 2010.

 

As part of this project, city staff have completed the construction documents for Phase 2 of project UT0702CS for the rehabilitation of the existing 8 inch vitrified clay pipe (VCP) sewer located on the east side of Michigan Street from 7th Street to 8th Street. Construction documents developed detail the installation of approximately 182 feet of 12 inch diameter SDR-26 PVC sewer, 35 feet of 8 inch diameter SDR-26 PVC sewer, and identify the limits of required point repairs and the installation of approximately 640 lineal feet of cured in place pipe (CIPP).

 

The project is anticipated to be substantially complete in early 2011 based on a project schedule of 70 working days. Final acceptance of the project will be contingent upon completion of punch-list items and final restoration of all disturbed areas. The project schedule includes allowances for pre-construction and public meetings between the award of the bid and notice to proceed.

 

Project Schedule

          Set Bid Date                      September 07, 2010

Pre-Bid Meeting                  September 21, 2010

Bid Opening                       September 28, 2010

          Award Bid                          October 05, 2010

          Notice to Proceed               November 2010

          Substantial Completion        February 2011

 

Project Funding:

Design and easement acquisition costs for the above referenced project are funded from the 2009 Department of Utilities non-bonded construction fund. Construction will be funded from the reallocation of previous Department of Utilities bond issues per resolution 6898 included as part of the agenda for the August 03, 2010 City Commission Meeting.

Recommendation

Set a bid date of September 28, 2010 for Bid No. B1050 Project UT0905CS, sanitary sewer main replacement for the 1100 block of Delaware Street, the 1500 block New Hampshire Street and the 700 block of Michigan Street.

 

Thank you for your assistance. Please advise if you have any questions.