Memorandum
City of Lawrence
Department of Public Works
TO: |
Charles F. Soules, Director of Public Works |
FROM: |
Mark Thiel, Assistant Public Works Director |
DATE: |
June 2, 2010 |
RE: |
Project No. PW0915 – Fairfield East Addition No. 1 |
|
Change Order No. 1 & No. 2 – Exchange Place / Fairfield Street Improvements |
|
June 8, 2010 Consent Agenda Item |
Please include the following item on the City Commission consent agenda for consideration at the June 8, 2010 meeting: Approve Change Order No. 1 & No. 2 – Exchange Place/Fairfield Street Improvements.
Project Funding. The current contract amount is $1,286,904.30. Change Order No. 1, in the amount of $4,170.39, is for the addition of quantities in materials. Change Order No. 2, in the amount of $5,131, is for asphalt oil adjustment pricing per contract. The project is complete and financed through a benefit district. The Benefit District is paying for 100% of the cost of the improvements and 0% by the City at large (Resolution No. 6842).
Action Request. Authorize the City Manager to sign and approve Change Order No. 1 and No. 2 for Project PW0915, Fairfield East Addition No. 1, Exchange Place & Fairfield Street, Street, Storm Sewer, and Waterline Improvements.
Attachments: Change Order #1