Memorandum
City of Lawrence
Utilities Department
TO: |
David L. Corliss – City Manager Cynthia Boecker - Assistant City Manager Diane Stoddard - Assistant City Manager |
FROM: |
Mike Lawless – Asst. Director of Utilities |
CC: |
Dave Wagner – Director of Utilities Philip Ciesielski – Asst. Director of Utilities Beth Frailey Krishtalka – Management Analyst |
Date: |
April 19, 2010 |
RE: |
Agenda Item – Purchase wastewater and water modeling software from Bentley Systems, Inc.
|
Please include the following item on the City Commission Agenda for consideration at the April 27, 2010 meeting:
Authorize Staff to purchase 1 license each of wastewater and water modeling software from Bentley Systems, Inc.
Project Description
The Wastewater Master Plan scope of services included the City selecting and purchasing modeling software to be used for this project as well as, the Water Master Plan. Selection of the software vendors to provide demonstrations started with establishing base criteria for the software and vendors to meet. The criteria included the following:
1. Commercially available
2. Vendor could supply dynamic sewer and water system models
3. GIS Interface
Only two software vendors met the criteria:
Bentley Systems and MWH Soft. Each vendor was invited to present a demonstration
of the software to Utilities and Public Works Department staff as well as,
Burns & McDonnell. Utilities GIS data for wastewater and water was provided
to the vendors. Each vendor was provided 4 hours to demonstrate the
capabilities and functionality of their products.
The demonstrations of each software were very comparable. Staff considered a number of different criteria in the evaluation of the software, some of which are listed below.
· Hydraulic Features Data Structure
· GIS Interface Multiple Platform
· Additional Modules Output Presentation
· Virtual Server Compatible VFD Capabilities
· Local Users Skeletonized Data Retention
· Initial Cost Maintenance Cost
After considerable discussion and checking references, staff concluded that the Bentley Systems software will provide the best and most cost effective solution for water and sewer system modeling for the City of Lawrence.
Initial Cost |
5 Year Cost |
|
|
1 License Each |
1 License Each |
MWH |
$ 42,000 |
$ 81,000 |
Bentley |
$ 35,350 |
$ 59,350 |
Project Funding:
Funding for the sewer modeling software was included in the 2009 Capital Improvement Program and funding for the water modeling software was included in the 2010 Capital Improvement Program.
Action Request: Authorize staff to purchase 1 license each of wastewater and water modeling software from Bentley Systems, Inc.
Thank you for your assistance. Please advise if you have any questions.