CITY OF LAWRENCE 
City Bid No. B09069 - Project No. PW0914 - Clinton Parkway Shared-Use Paths
BID TAB - Bid Date:  December 15, 2009
Engineer's Estimate:  Base Bid - $633,850.00; Alternate Bid "A" - $216,046.00; 
                                       Alternate Bid "B" - $147,692.00          
R. D. Johnson Excavating Graybeal Construction Miller Paving & Const. Kansas Heavy Const. MEGA Industries Corp. Pavers, Inc. H. B. Construction, Inc. Emery Sapp & Sons, Inc. King's Construction VF Anderson Builders
ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT
  Base Bid - Paths 1, 2, and 3                                            
1 Mobilization L.S. 1  $  16,000.00  $     16,000.00  $    8,850.00  $      8,850.00  $    7,000.00  $         7,000.00  $    9,000.00  $      9,000.00  $  21,000.00  $    21,000.00  $  64,119.78  $    64,119.78  $  30,140.00  $    30,140.00  $  35,000.00  $    35,000.00  $  23,000.00  $    23,000.00  $  13,000.00  $    13,000.00
2 Grading and Compaction of Earthwork L.S. 1  $  16,800.00  $     16,800.00  $  15,952.00  $    15,952.00  $  33,500.00  $       33,500.00  $  33,600.00  $    33,600.00  $  38,000.00  $    38,000.00  $  14,009.62  $    14,009.62  $  44,460.00  $    44,460.00  $  24,000.00  $    24,000.00  $  70,000.00  $    70,000.00  $  80,000.00  $    80,000.00
3 Removal of Exist. Asphalt Path and Related Concrete Pvmt. SY 9309  $           3.00  $     27,927.00  $           1.59  $    14,801.31  $           5.00  $       46,545.00  $           2.50  $    23,272.50  $           2.00  $    18,618.00  $           3.13  $    29,137.17  $           3.96  $    36,863.64  $           2.40  $    22,341.60  $           2.53  $    23,551.77  $           6.00  $    55,854.00
4 Fiber Reinforced Concrete Shared Use Path (6" x 10') SY 12122  $         29.25  $   354,568.50  $         30.15  $  365,478.30  $         27.45  $     332,748.90  $         29.90  $  362,447.80  $         29.00  $  351,538.00  $         29.54  $  358,083.88  $         29.00  $  351,538.00  $         28.50  $  345,477.00  $         30.44  $  368,993.68  $         33.00  $  400,026.00
5 Concrete Sidewalk Ramp (10') Ea. 7  $    1,250.00  $       8,750.00  $    4,522.00  $    31,654.00  $    1,725.00  $       12,075.00  $    2,600.00  $    18,200.00  $    1,650.00  $    11,550.00  $    1,034.31  $      7,240.17  $    1,600.00  $    11,200.00  $    2,400.00  $    16,800.00  $    1,250.00  $      8,750.00  $    1,300.00  $      9,100.00
6 Concrete Sidewalk  (4") SY 10  $         30.00  $          300.00  $         91.50  $         915.00  $         56.25  $            562.50  $         59.00  $         590.00  $         53.00  $         530.00  $         42.84  $         428.40  $         36.00  $         360.00  $         47.00  $         470.00  $         25.00  $         250.00  $       100.00  $      1,000.00
7 Remove and Replace 9' x 3.5' Storm Sewer Curb Inlet Top Ea. 1  $    2,400.00  $       2,400.00  $    2,590.00  $      2,590.00  $    2,405.00  $         2,405.00  $    2,600.00  $      2,600.00  $    2,800.00  $      2,800.00  $    2,281.79  $      2,281.79  $    2,819.00  $      2,819.00  $    3,800.00  $      3,800.00  $    2,200.00  $      2,200.00  $    2,200.00  $      2,200.00
8 Remove and Replace 10' x 3.5' Storm Sewer Curb Inlet Top Ea. 2  $    2,500.00  $       5,000.00  $    2,620.00  $      5,240.00  $    2,465.00  $         4,930.00  $    2,700.00  $      5,400.00  $    2,950.00  $      5,900.00  $    2,303.66  $      4,607.32  $    2,884.00  $      5,768.00  $    3,900.00  $      7,800.00  $    2,350.00  $      4,700.00  $    2,400.00  $      4,800.00
9 Remove and Replace 10' x 4.5' Storm Sewer Curb Inlet Top Ea. 2  $    2,600.00  $       5,200.00  $    2,620.00  $      5,240.00  $    2,650.00  $         5,300.00  $    2,800.00  $      5,600.00  $    3,100.00  $      6,200.00  $    2,415.67  $      4,831.34  $    2,956.00  $      5,912.00  $    3,900.00  $      7,800.00  $    2,400.00  $      4,800.00  $    2,500.00  $      5,000.00
10 Remove and Replace 14' x 3.5' Storm Sewer Curb Inlet Top Ea. 6  $    3,000.00  $     18,000.00  $    3,050.00  $    18,300.00  $    2,780.00  $       16,680.00  $    2,900.00  $    17,400.00  $    3,500.00  $    21,000.00  $    2,756.84  $    16,541.04  $    3,258.00  $    19,548.00  $    4,000.00  $    24,000.00  $    3,500.00  $    21,000.00  $    2,600.00  $    15,600.00
11 Remove and Replace 15' x 4.5' Storm Sewer Curb Inlet Top Ea. 5  $    3,400.00  $     17,000.00  $    3,100.00  $    15,500.00  $    3,065.00  $       15,325.00  $    3,700.00  $    18,500.00  $    4,000.00  $    20,000.00  $    3,102.76  $    15,513.80  $    3,510.00  $    17,550.00  $    4,200.00  $    21,000.00  $    3,900.00  $    19,500.00  $    2,700.00  $    13,500.00
12 Seeding, Fertilizing and Mulching L.S. 1  $    7,000.00  $       7,000.00  $    4,400.00  $      4,400.00  $    3,200.00  $         3,200.00  $  12,500.00  $    12,500.00  $    4,000.00  $      4,000.00  $    8,230.01  $      8,230.01  $    4,620.00  $      4,620.00  $  21,000.00  $    21,000.00  $  10,000.00  $    10,000.00  $    8,000.00  $      8,000.00
13 Traffic Control L.S. 1  $    6,000.00  $       6,000.00  $    2,285.00  $      2,285.00  $    3,800.00  $         3,800.00  $    2,200.00  $      2,200.00  $    6,600.00  $      6,600.00  $    7,235.19  $      7,235.19  $    6,254.00  $      6,254.00  $    9,300.00  $      9,300.00  $    2,000.00  $      2,000.00  $    6,300.00  $      6,300.00
14 Construction Staking L.S. 1  $    2,500.00  $       2,500.00  $           0.01  $             0.01  $    3,895.00  $         3,895.00  $       500.00  $         500.00  $    3,600.00  $      3,600.00  $    3,879.86  $      3,879.86  $    3,000.00  $      3,000.00  $    3,400.00  $      3,400.00  $    1,500.00  $      1,500.00  $    5,200.00  $      5,200.00
15 Signing (W7-5), 18" x 18" Ea. 2  $       200.00  $          400.00  $         85.00  $         170.00  $       295.00  $            590.00  $       200.00  $         400.00  $       200.00  $         400.00  $       223.09  $         446.18  $       286.00  $         572.00  $       200.00  $         400.00  $         85.00  $         170.00  $       500.00  $      1,000.00
16 36" Solid White Crosswalk Line LF 590  $         12.50  $       7,375.00  $           9.54  $      5,628.60  $         12.65  $         7,463.50  $         10.00  $      5,900.00  $         13.00  $      7,670.00  $         14.47  $      8,537.30  $         12.10  $      7,139.00  $         13.00  $      7,670.00  $           9.54  $      5,628.60  $         37.00  $    21,830.00
17 24" Solid White Stop Line LF 156  $           9.50  $       1,482.00  $           9.54  $      1,488.24  $           9.20  $         1,435.20  $         10.00  $      1,560.00  $         10.00  $      1,560.00  $         10.85  $      1,692.60  $           8.80  $      1,372.80  $         10.00  $      1,560.00  $           9.54  $      1,488.24  $         24.00  $      3,744.00
18 Existing Pavement Marking Removal SF 954  $           2.50  $       2,385.00  $           1.00  $         954.00  $           2.30  $         2,194.20  $           1.00  $         954.00  $           2.00  $      1,908.00  $           2.41  $      2,299.14  $           2.20  $      2,098.80  $           2.00  $      1,908.00  $           1.00  $         954.00  $           2.00  $      1,908.00
Total Base Bid    $   499,087.50    $  499,446.46    $     499,649.30    $  520,624.30    $  522,874.00    $  549,114.59    $  551,215.24    $  553,726.60    $  568,486.29    $  648,062.00
NOTE: Contract will be awarded to the lowest "Base Bid"
     
ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT
  Alternate Bid 'A'                                        
1 Mobilization L.S. 1  $    6,000.00  $       6,000.00  $    3,431.00  $      3,431.00  $    3,000.00  $         3,000.00  $    2,650.00  $      2,650.00  $    9,000.00  $      9,000.00  $  19,787.69  $    19,787.69  $  15,724.00  $    15,724.00  $  13,000.00  $    13,000.00  $    7,750.00  $      7,750.00  $    8,000.00  $      8,000.00
2 Grading and Compaction of Earthwork L.S. 1  $    7,500.00  $       7,500.00  $    5,971.00  $      5,971.00  $  12,349.75  $       12,349.75  $  14,480.00  $    14,480.00  $  12,000.00  $    12,000.00  $  10,286.23  $    10,286.23  $  19,000.00  $    19,000.00  $    9,000.00  $      9,000.00  $  27,500.00  $    27,500.00  $  47,000.00  $    47,000.00
3 Removal of Exist. Asphalt Path and Related Concrete Pvmt. SY 3267  $           3.40  $     11,107.80  $           2.20  $      7,187.40  $           5.00  $       16,335.00  $           4.00  $    13,068.00  $           2.00  $      6,534.00  $           3.26  $    10,650.42  $           4.25  $    13,884.75  $           3.25  $    10,617.75  $           2.75  $      8,984.25  $           6.00  $    19,602.00
4 Fiber Reinforced Concrete Shared Use Path (6" x 10') SY 4252  $         34.00  $   144,568.00  $         31.95  $  135,851.40  $         27.45  $     116,717.40  $         29.90  $  127,134.80  $         29.00  $  123,308.00  $         30.09  $  127,942.68  $         29.00  $  123,308.00  $         28.50  $  121,182.00  $         32.46  $  138,019.92  $         33.00  $  140,316.00
5 Concrete Sidewalk Ramp (10') Ea. 6  $    1,250.00  $       7,500.00  $    4,777.00  $    28,662.00  $    1,725.00  $       10,350.00  $    2,900.00  $    17,400.00  $    1,650.00  $      9,900.00  $    1,036.48  $      6,218.88  $    1,600.00  $      9,600.00  $    2,400.00  $    14,400.00  $    1,250.00  $      7,500.00  $    1,300.00  $      7,800.00
6 Concrete Sidewalk  (4") SY 5  $         30.00  $          150.00  $         95.75  $         478.75  $         56.25  $            281.25  $         60.00  $         300.00  $         53.00  $         265.00  $         45.94  $         229.70  $         50.00  $         250.00  $         47.00  $         235.00  $         25.00  $         125.00  $       100.00  $         500.00
7 Remove and Replace 10' x 3.5' Storm Sewer Curb Inlet Top Ea. 1  $    2,500.00  $       2,500.00  $    2,720.00  $      2,720.00  $    2,585.00  $         2,585.00  $    2,700.00  $      2,700.00  $    2,950.00  $      2,950.00  $    2,264.63  $      2,264.63  $    2,884.00  $      2,884.00  $    3,800.00  $      3,800.00  $    2,350.00  $      2,350.00  $    2,400.00  $      2,400.00
8 Remove and Replace 14' x 3.5' Storm Sewer Curb Inlet Top Ea. 7  $    3,000.00  $     21,000.00  $    3,200.00  $    22,400.00  $    2,780.00  $       19,460.00  $    3,400.00  $    23,800.00  $    3,500.00  $    24,500.00  $    2,818.82  $    19,731.74  $    3,258.00  $    22,806.00  $    4,200.00  $    29,400.00  $    3,550.00  $    24,850.00  $    2,600.00  $    18,200.00
9 Seeding, Fertilizing and Mulching L.S. 1  $    6,800.00  $       6,800.00  $    1,540.00  $      1,540.00  $    2,900.00  $         2,900.00  $    5,000.00  $      5,000.00  $    1,500.00  $      1,500.00  $    2,962.80  $      2,962.80  $    2,000.00  $      2,000.00  $    7,300.00  $      7,300.00  $    3,500.00  $      3,500.00  $    5,000.00  $      5,000.00
10 Traffic Control L.S. 1  $    1,850.00  $       1,850.00  $    1,025.00  $      1,025.00  $    1,000.00  $         1,000.00  $    1,200.00  $      1,200.00  $       900.00  $         900.00  $    1,024.98  $      1,024.98  $    1,908.00  $      1,908.00  $    2,700.00  $      2,700.00  $    1,025.00  $      1,025.00  $    4,000.00  $      4,000.00
11 Construction Staking L.S. 1  $    3,000.00  $       3,000.00  $           0.01  $             0.01  $    1,500.00  $         1,500.00  $       200.00  $         200.00  $    1,400.00  $      1,400.00  $    1,493.16  $      1,493.16  $    2,000.00  $      2,000.00  $    1,300.00  $      1,300.00  $    2,500.00  $      2,500.00  $    4,000.00  $      4,000.00
12 36" Solid White Crosswalk Line LF 359  $         12.50  $       4,487.50  $           9.54  $      3,424.86  $         13.80  $         4,954.20  $         10.00  $      3,590.00  $         13.00  $      4,667.00  $         14.47  $      5,194.73  $         13.20  $      4,738.80  $         13.00  $      4,667.00  $           9.54  $      3,424.86  $         37.00  $    13,283.00
13 24" Solid White Stop Line LF 96  $           9.50  $          912.00  $           9.54  $         915.84  $           9.20  $            883.20  $         10.00  $         960.00  $         10.00  $         960.00  $         10.85  $      1,041.60  $           8.80  $         844.80  $         10.00  $         960.00  $           9.54  $         915.84  $         24.00  $      2,304.00
14 Existing Pavement Marking Removal SF 806  $           2.50  $       2,015.00  $           1.00  $         806.00  $           3.20  $         2,579.20  $           1.00  $         806.00  $           2.00  $      1,612.00  $           2.41  $      1,942.46  $           2.20  $      1,773.20  $           2.00  $      1,612.00  $           1.00  $         806.00  $           2.00  $      1,612.00
Total Alternate Bid 'A' Section    $   219,390.30    $  214,413.26    $     194,895.00    $  213,288.80    $  199,496.00    $  210,771.70    $  220,721.55    $  220,173.75    $  229,250.87    $  274,017.00
                                               
ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT
  Alternate Bid 'B'                                        
1 Mobilization L.S. 1  $    3,000.00  $       3,000.00  $    3,266.25  $      3,266.25  $    3,700.00  $         3,700.00  $    1,930.00  $      1,930.00  $    6,000.00  $      6,000.00  $  17,172.69  $    17,172.69  $    7,270.00  $      7,270.00  $  13,000.00  $    13,000.00  $    5,000.00  $      5,000.00  $    6,000.00  $      6,000.00
2 Grading and Compaction of Earthwork L.S. 1  $    5,000.00  $       5,000.00  $    3,611.00  $      3,611.00  $    9,000.00  $         9,000.00  $    9,630.00  $      9,630.00  $    8,000.00  $      8,000.00  $    3,156.79  $      3,156.79  $  10,415.00  $    10,415.00  $    5,500.00  $      5,500.00  $  20,000.00  $    20,000.00  $  32,000.00  $    32,000.00
3 Removal of Exist. Asphalt Path and Related Concrete Pvmt. SY 2221  $           3.40  $       7,551.40  $           1.60  $      3,553.60  $           5.00  $       11,105.00  $           4.10  $      9,106.10  $           2.00  $      4,442.00  $           3.23  $      7,173.83  $           4.25  $      9,439.25  $           2.10  $      4,664.10  $           2.93  $      6,507.53  $           6.00  $    13,326.00
4 Fiber Reinforced Concrete Shared Use Path (6" x 10') SY 2823  $         34.00  $     95,982.00  $         31.95  $    90,194.85  $         27.45  $       77,491.35  $         29.90  $    84,407.70  $         29.00  $    81,867.00  $         30.20  $    85,254.60  $         29.00  $    81,867.00  $         28.50  $    80,455.50  $         31.25  $    88,218.75  $         33.00  $    93,159.00
5 Concrete Sidewalk Ramp (10') Ea. 5  $    1,250.00  $       6,250.00  $    4,777.00  $    23,885.00  $    1,725.00  $         8,625.00  $    3,200.00  $    16,000.00  $    1,650.00  $      8,250.00  $    1,033.80  $      5,169.00  $    1,600.00  $      8,000.00  $    2,400.00  $    12,000.00  $    1,250.00  $      6,250.00  $    1,300.00  $      6,500.00
6 Concrete Sidewalk  (4") SY 5  $         30.00  $          150.00  $         95.75  $         478.75  $         56.25  $            281.25  $         60.00  $         300.00  $         53.00  $         265.00  $         45.94  $         229.70  $         50.00  $         250.00  $         47.00  $         235.00  $         25.00  $         125.00  $       100.00  $         500.00
7 Modify Existing Median Nose L.S. 1  $    2,500.00  $       2,500.00  $    1,922.00  $      1,922.00  $    1,075.00  $         1,075.00  $    3,400.00  $      3,400.00  $    1,100.00  $      1,100.00  $    1,660.47  $      1,660.47  $    1,500.00  $      1,500.00  $    5,100.00  $      5,100.00  $    3,000.00  $      3,000.00  $    2,000.00  $      2,000.00
8 Remove and Replace 9' x 3' Storm Sewer Curb Inlet Top Ea. 2  $    2,300.00  $       4,600.00  $    2,710.00  $      5,420.00  $    2,345.00  $         4,690.00  $    2,600.00  $      5,200.00  $    2,750.00  $      5,500.00  $    2,192.27  $      4,384.54  $    2,819.00  $      5,638.00  $    4,000.00  $      8,000.00  $    2,150.00  $      4,300.00  $    2,200.00  $      4,400.00
9 Remove and Replace 14' x 3' Storm Sewer Curb Inlet Top Ea. 4  $    2,900.00  $     11,600.00  $    3,200.00  $    12,800.00  $    2,750.00  $       11,000.00  $    3,400.00  $    13,600.00  $    3,500.00  $    14,000.00  $    2,744.69  $    10,978.76  $    3,258.00  $    13,032.00  $    4,100.00  $    16,400.00  $    3,400.00  $    13,600.00  $    2,600.00  $    10,400.00
10 Seeding, Fertilizing and Mulching L.S. 1  $    2,500.00  $       2,500.00  $    1,540.00  $      1,540.00  $    3,000.00  $         3,000.00  $    3,000.00  $      3,000.00  $    1,000.00  $      1,000.00  $    1,975.20  $      1,975.20  $    2,000.00  $      2,000.00  $    5,000.00  $      5,000.00  $    3,000.00  $      3,000.00  $    4,000.00  $      4,000.00
11 Traffic Control L.S. 1  $    1,750.00  $       1,750.00  $    1,025.00  $      1,025.00  $    1,000.00  $         1,000.00  $    1,200.00  $      1,200.00  $       800.00  $         800.00  $       904.39  $         904.39  $    1,908.00  $      1,908.00  $    2,600.00  $      2,600.00  $    1,025.00  $      1,025.00  $    4,000.00  $      4,000.00
12 Construction Staking L.S. 1  $    1,750.00  $       1,750.00  $           0.01  $             0.01  $    1,100.00  $         1,100.00  $       200.00  $         200.00  $    1,000.00  $      1,000.00  $    1,081.66  $      1,081.66  $    2,000.00  $      2,000.00  $    1,000.00  $      1,000.00  $       500.00  $         500.00  $    3,000.00  $      3,000.00
13 36" Solid White Crosswalk Line LF 479  $         12.50  $       5,987.50  $           9.54  $      4,569.66  $         13.80  $         6,610.20  $         10.00  $      4,790.00  $         13.00  $      6,227.00  $         14.47  $      6,931.13  $         13.20  $      6,322.80  $         13.00  $      6,227.00  $           9.54  $      4,569.66  $         37.00  $    17,723.00
14 24" Solid White Stop Line LF 110  $           9.50  $       1,045.00  $           9.54  $      1,049.40  $           9.20  $         1,012.00  $         10.00  $      1,100.00  $         10.00  $      1,100.00  $         10.85  $      1,193.50  $           8.80  $         968.00  $         10.00  $      1,100.00  $           9.54  $      1,049.40  $         24.00  $      2,640.00
15 Existing Pavement Marking Removal SF 20  $           2.00  $            40.00  $           1.00  $           20.00  $         13.00  $            260.00  $           1.00  $           20.00  $           2.00  $           40.00  $           2.41  $           48.20  $           2.20  $           44.00  $           2.00  $           40.00  $           1.00  $           20.00  $           2.00  $           40.00
Total Alternate Bid 'B' Section    $   149,705.90    $  153,335.52    $     139,949.80    $  153,883.80    $  139,591.00    $  147,314.46    $  150,654.05    $  161,321.60    $  157,165.34    $  199,688.00