Memorandum
City of Lawrence
Public Works
TO: |
David L. Corliss, City Manager |
FROM: |
David P. Cronin, P.E., Project Engineer |
CC: |
Cynthia Boecker, Diane Stoddard, Chuck Soules, Shoeb Uddin |
Date: |
November 4, 2009 |
RE: |
New York Street – 9th to 12th St. Brick Street Reconstruction Set Bid Date |
Please include the following item on the City Commission Regular Agenda for consideration at the November 10, 2009 meeting.
Project Description
This project will include the brick restoration of New York Street from 9th Street south to 12th Street. The street is currently a brick street with asphalt overlay. The pavement will be removed; the bricks will be cleaned to remove the asphalt, and salvaged. The new pavement section will include a flyash treated subgrade, 7” asphalt base, 1” of sand and brick surface course. Included with this project is reconstruction of intersections on New York Street at 9th, 10th, 11th and 12th St.
In response to the Commissions inquiry with respect to using local labor KDOT has responded: The Federal Highway Administration (FHWA) requires that Federal-aid contracts be awarded on the basis of full and open competition. The exclusion of nonlocal labor forces is noncompetitive and may increase the cost of the project. Even though some states and local public agencies have implemented policies which encourage or mandate the use of local employment of local contracting, Federal-aid contact documents should contain specific provisions that state such preferences are not allowed.
Project History
New York Street brick street reconstruction project was selected in March 2009 by the Kansas Department of Transportation for Transportation Enhancement (TE) funding under the American Recovery and Reinvestment Act (ARRA). The award amount is fixed at $946,827.75.
Project Funding
The project is being funded 100% by KDOT with no city funds up to the award amount of $946,827.75. The project cost does not include the cost of engineering design or construction engineering services. Public Works staff is designing the project in-house and will be providing construction inspection. No property acquisition is required.
Project Status / Schedule
Advertise for Bids: November 13, 2009
Open Bids: December 15, 2009
Award Contract: December 29, 2009
Construction: Spring 2010
Action Request
Set a bid date of December 15, 2009 for PW0913, New York Street -9th to 12th St. Brick Street Reconstruction.