Concrete Pavement & Curb & Gutter

 

The overall quantity of 3365.7 SY for 10” NRDJ along Kasold & 197.4 SY for E 1200 Road at $60/SY equates to a cost of $213,786.   (The right turn lane by itself has 366.1 SY of concrete pavement, which equates to $21,966.  This cost is included in the overall quantity.  The center turn lane by itself has 560.4 SW of concrete pavement, which equates to $33,624.  This cost is included in the overall quantity.)

 

In terms of Curb & Gutter, there is approximately 1,059 LF of curb & gutter, and at $18/LF, this equates to a cost of $19,062.

 

Fly Ash Treated Subgrade

 

There is 3636.0 SY of 9” Fly Ash Treated Subgrade in the intersection area and at $5.00/SY, this equates to $18,180

 

Sidewalk/Recreation Trail

 

There is 285.0 SY of 4” concrete sidewalk (W=6’) at $35/SY equates to $9,975.

 

For the recreation trail, there are 308.6 SY at $40/SY, which equates to $12,344.

 

At the intersection of E 1200 Road and Kasold, there are two sidewalk ramps equally 20.8 SY, and at $210/SY, this equates to $4,368.

                                                                                    ______________________

                                                                                          TOTAL    $277,715