City of Lawrence
Public Works Department
MEMORANDUM
DATE: August 26, 2009
TO: David L. Corliss
City Manager
FROM: David P. Cronin, P.E.
Project Engineer
On August 25, 2009, the City of Lawrence opened proposals for the following:
City Bid No. B09049
Project PW0901 – KLINK – 23rd Street (K-10) – From Ousdahl Road to Barker Avenue
Milling, Overlay, Pavement Marking, Video Detection System
VENDOR |
TOTAL BID |
Engineer’s Estimate |
$576,857.75 |
Bettis Asphalt & Construction, Inc. |
$556,399.25 |
LRM Industries, Inc. |
$557,651.10 |
Sunflower Paving, Inc. |
$560,273.49 |
Hamm, Inc. |
$675,067.53 |
Project Details: The project includes a 2” mill and overlay of 23rd Street from Ousdahl Road to Barker Avenue. Also included is pavement marking, the addition of an access ramp on the northeast corner of 23rd Street & Louisiana Street, and the installation of a video detection system at the intersections of Ousdahl Road, Alabama Street, Louisiana Street and Massachusetts Street. After completion every intersection through the project will use a video detection system. A video detection system has already been installed at 23rd Street & Barker Avenue and a video detection system is being installed at 23rd Street & Naismith Drive as part of the 2009 Mill, Overlay & Curb Repair, Phase 2 project.
Project Schedule: Construction is planned to begin late September, shortly after the contract is signed. Depending on weather conditions, the project is expected to be completed within about 2 weeks after starting construction. The contractor will notify neighboring businesses prior to work and City staff is anticipating asphalt operations to occur at night.
Project Funding: The maximum State participation in the cost of construction is $200,000 and the balance of cost will be paid for from the City sales tax reserve fund.
Action Request. Approve bid from Bettis Asphalt & Construction, Inc. for Project PW0901, KLINK 23rd Street (K-10) – From Ousdahl Road to Barker Avenue in the amount of $556,399.25 provided the contractor can meet the terms established in the contract documents.
Attachment: Bid Tab
cc: Cynthia Boecker
Diane Stoddard
Chuck Soules
Mark Thiel
Jonathan Douglass
Alan Landis
Tammy Bennett